MARQUESA

MARQUESA is a 1999 passenger vessel (inspected). The Coast Guard has recorded 26 inspections since 2016, most recently in December 2025, along with 107 deficiencies, 2 operational controls and 10 casualty investigations between 2006 and 2021.

Records from 2006 to 2025. Most recent: inspection, 10 December 2025.

Built
1999
Last inspected
10 December 2025
Documentation
Valid · documentation file of 10 August 2026
Controls
None recorded without a removal date

Identity

WCZ6117
498526
Flag
UNITED STATES
Maury page id
psix-498526

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 2016.

Inspections, by type

…with no type recorded4
Years with a record 10 calendar years (2016–2025)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. The counts in the strip above are the same counts; this table splits the inspections by the kind of activity recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Documentation record

Registered dimensions (L × B × D)67.0 ft × 34.0 ft × 8.0 ft
Registered tonnagegross 32 / net 28
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderMULTIHULL TECHNOLOGIES INC · KEY WEST, FL, UNITED STATES · built 1999
Hull materialFRP (Fiberglass)
PropulsionDiesel Reduction
Hull shapeSail (Distinct Keel)
Hull configurationTwin Hull
Hailing portKEY WEST, FL
Trade endorsementsCoastwise, unrestricted, Fishery, Recreational, Registry
DocumentationValid · issued 17 March 2026 · expires 31 March 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it32 - Simplified, Gross Ton
28 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Vessel history report
Every record for this hull, in one document — $299

What it gives that this page does not: the whole record in one dated, citable document — every line with its Coast Guard activity id, the retrieval date on the cover, built to print to PDF with its page breaks — that a surveyor can attach and a lender can file. The same facts as this page, complete and in one file.

Every recorded inspection, 2016 to 2026 for this class, in one chronology · every deficiency, with system, dates and resolution · operational controls imposed and removed · every name this hull has been recorded under · the vessels it was inspected alongside, and when · how its record compares with hulls of similar age and size, as a fact about the population and never a judgement about this vessel.

Read one first, in full: a forty-year chronology · a hull that changed operators four times · the sparse case, shown as an example, not for sale.

A request, not a checkout: leave an email and Maury replies once, with the dated document for this hull and a Stripe invoice for $299. Nothing is charged before the document is in your hands.

Inspection history · 26

10 December 2025 Deficiency Check · Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 8291354
10 October 2025 Examination of Repairs · Drydock Exam · Internal Structural Exam
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 8247278
8 April 2025 In-Service Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 8108039
24 October 2024 COI Inspection · Deficiency Check
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 8022227
23 January 2024 Annual Inspection · Deficiency Check
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7858806
24 October 2023 Drydock Exam · In-Service Inspection · Examination of Repairs · Internal Structural Exam
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7806997
29 June 2023 In-Service Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7756869
7 December 2022 Deficiency Check · Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7600770
23 June 2022 In-Service Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7484704
24 January 2022 Annual Inspection · Deficiency Check
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7383128
30 September 2021 Internal Structural Exam · In-Service Inspection · Examination of Repairs · Drydock Exam
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7300424
24 April 2021 Type not recorded
No type recorded · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7182958
24 October 2020 Type not recorded
No type recorded · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7084098
7 October 2020 Deficiency Check · Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7070050
29 September 2020 Type not recorded
No type recorded · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7067879
28 September 2020 Damage Survey
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7066904
20 September 2020 Type not recorded
No type recorded · Sector Key West · USCG Southeast District (CGD-SE) · Activity 7067909
31 October 2019 COI Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 6837375
4 September 2019 Internal Structural Exam · Deficiency Check · Drydock Exam
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 6790754
16 July 2019 Administrative Inspection
Administrative · Sector Key West · USCG Southeast District (CGD-SE) · Activity 6752549
8 January 2019 Deficiency Check · Administrative Inspection · DAPI Audit · Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 6585440
16 January 2018 Annual Inspection · DAPI Audit · Deficiency Check · Administrative Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 6339564
12 October 2017 Examination of Repairs · Drydock Exam · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6229495
5 January 2017 Construction Oversight · Administrative Inspection · Plan Review "T" Boat
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6106706
15 December 2016 Administrative Inspection · DAPI Audit · Deficiency Check · Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 6058148
21 January 2016 Annual Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 5795890

Deficiency record · 107

07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 10 December 2025 Resolved
The automatic shutdown function for the pre-engineered fixed gas fire extinguishing system in the starboard engine room is not working.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 10 December 2025
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 10 December 2025 Resolved
The override function pre-engineered fixed gas fire extinguishing system in the starboard engine room is not working.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 10 December 2025
04 - Emergency Systems › N/A - No Subsystem › Water level indicator
Issued 10 December 2025 Resolved
Provide a visual indicator for the port bilge high level alarm (the audible indicator is functional).
Action required: 16 - Rectify deficiencies w/in 14 days
Due 24 December 2025
Resolved 10 December 2025
11 - Life Saving Appliances › N/A - No Subsystem › Distress flares
Issued 10 December 2025 Resolved
Provide 3 additional red flare or orange smoke distress signals so there are a total of 12 distress signals on board.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 24 December 2025
Resolved 10 December 2025
05 - Radio Communications › N/A - No Subsystem › Satellite EPIRB 406MHz/1.6GHz
Issued 24 October 2024 Resolved
The hydrostatic release for the EPIRB expired Aug 2024. Replace hydrostatic release.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2024
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 24 October 2024 Resolved
The port engine would not shutdown during the testing of the port engine room pre-engineered fixed gas fire extinguishing system. Prove proper shutdown and override of system.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2024
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 24 October 2024 Resolved
Provide an updated copy of the vessel's rigging inventory.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 November 2024
Resolved 24 October 2024
04 - Emergency Systems › N/A - No Subsystem › Public address system
Issued 24 October 2024 Resolved
Provide a public address system that is audible throughout the passenger areas.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 November 2024
Resolved 5 November 2024
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 24 October 2024 Resolved
Seal the electrical run in the aft bulkhead of the port forward compartment to make the bulkhead watertight.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 November 2024
Resolved 5 November 2024
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 24 October 2024 Resolved
Provide a gauge at the fire pump outlet to show the pump can provide a pressure of not less than 60 psi.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 November 2024
Resolved 5 November 2024
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 23 January 2024 Resolved
The pull cable for the port fuel shutoff valve is stuck and the crewmember could not actuate the valve.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 23 January 2024
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 23 January 2024 Resolved
The reset device for the pre-engineered fixed gas fire extinguishing system for the starboard engine would not allow the engine to start in the override setting.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 23 January 2024
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 23 January 2024 Resolved
Install covers on the port and starboard battery boxes.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 31 January 2024
03 - Water/Weathertight Conditions › N/A - No Subsystem › Machinery space openings
Issued 23 January 2024 Resolved
Seal cable run opening in the port engine compartment aft bulkhead.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 31 January 2024
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 23 January 2024 Resolved
Place the wire connection for the port engine local start switch within an enclosure.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 31 January 2024
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 23 January 2024 Resolved
Mark the vessel's name on the ring life buoy.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 31 January 2024
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 23 January 2024 Resolved
Rigging inspection log should indicate what type of rigging inspection was conducted (monthly, quarterly, etc.) as described in the vessel's Rigging PMP.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 31 January 2024
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 7 December 2022 Resolved
Vessel's port fixed power bilge pump is inoperable and would not take suction to dewater the port hull. Prove proper operation prior to carrying passengers.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 7 December 2022
05 - Radio Communications › N/A - No Subsystem › Satellite EPIRB 406MHz/1.6GHz
Issued 7 December 2022 Resolved
Vessel's EPIRB registration is expired and vessel is not equipped with primary lifesaving. Provide valid EPIRB registration prior to carrying passengers.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 7 December 2022
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 December 2022 Resolved
1 of 3 ring life buoys is no longer in serviceable condition. Replace ring life buoy.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 12 December 2022
09 - Working and Living Conditions › 092 - Working Conditions › Pipes, wires (insulation)
Issued 7 December 2022 Resolved
Suitably insulate the hot sections of the port and starboard engine exhaust pipe that are currently exposed.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 12 December 2022
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 24 January 2022 Resolved
Provide correct EPIRB registration.
Condition: Invalid
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 February 2022
Resolved 25 February 2022
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 24 January 2022 Resolved
Repair gaskets to engine room doors.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 February 2022
Resolved 25 February 2022
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 24 January 2022 Resolved
Fill cable passthroughs with appropriate fire retardant material.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 February 2022
Resolved 25 February 2022
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 October 2020 Resolved
Replace the lifeline on the ring life buoy located at the operating station. New lifeline must be at least 60 feet in length and meet the requirements in 46 CFR 180.70(c).
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 8 October 2020
Resolution: Received e-mailed photo of a 70' synthetic line attached to the ring life buoy.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 October 2020 Resolved
Replace the floating waterlight lanyard on the ring life buoy located at the operating station. New lanyard must be between 3 feet and 6 feet in length and meet the requirements of 46 CFR 180.70(d).
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 8 October 2020
Resolution: Received e-mailed photo of a 6' lanyard with clip attached to the floating waterlight.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 28 September 2020 Resolved
Vessel sustained damage to the hull in way of the starboard rudder and snapped the rudder in half due to an engine casualty resulting in a loss of forward propulsion. Repairs to both the hull and the rudder must be completed to the satisfaction of the OCMI prior to the carriage of passengers.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 September 2020
Resolved 19 October 2020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 28 September 2020 Resolved
Vessel sustained an engine casualty rendering forward propulsion inoperable. Operator must diagnose and identify cause of casualty, affect repairs, and conduct a successful sea trial prior to the carriage of passengers.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 September 2020
Resolved 19 October 2020
03 - Water/Weathertight Conditions › N/A - No Subsystem › Windows, sidescuttles and deadlights
Issued 31 October 2019 Resolved
Provide closure device to make for Port collision bulkhead watertight, missing 8’ round plate.
Action required: 10 - Deficiency Rectified
Resolved 31 October 2019
Resolution: Cover located and installed before end of inspection
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 31 October 2019 Resolved
Repair/replace ventilation closure device for Port engine room, closure is inoperable and unable to prevent the loss of the fire extinguishing agent.
Action required: 10 - Deficiency Rectified
Resolved 31 October 2019
Resolution: Closure device repaired prior to completion of inspection.
04 - Emergency Systems › N/A - No Subsystem › Fire drills
Issued 31 October 2019 Resolved
Drills required (fire/MOB/abandon ship) shall be logged and made available for USCG upon request. Entry shall include date, general description of drill and training topics (lessons learned) at a minimum.
Action required: 10 - Deficiency Rectified
Resolved 31 October 2019
Resolution: Educated captain and vessel rep, special note added.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 31 October 2019 Resolved
Secure CO2 tank located behind the bar to prevent an accidental release.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 31 October 2019 Resolved
Provide first aid kit with required contents per 46 CFR 160.041
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 31 October 2019 Resolved
Repair/replace STBD aft ring life buoy, buoy outer wrap missing exposing floatation material to sun damage and water intrusion
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 31 October 2019 Resolved
Each floating water light attached to a Life float shall be 18 feet in length, replace line with 18ft line
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 31 October 2019 Resolved
Join both Port and STBD metallic fuel fill fitting to tanks with a conductor to protect against generation of a static charge
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 31 October 2019 Resolved
Secure both Port and STBD engine starting batteries to prevent against shifting with roll and pitch of vessel
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
10 - Safety of Navigation › N/A - No Subsystem › Charts
Issued 31 October 2019 Resolved
Provide updated marine chart of appropriate scale for area of operation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 31 October 2019 Resolved
Secure penetration in Port engine room bulkhead, penetration allows for fire extinguishing agent to be released upon activation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 31 October 2019 Resolved
Reattach securing straps to potable water tank in port compartment
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
09 - Working and Living Conditions › 092 - Working Conditions › Protection machinery
Issued 31 October 2019 Resolved
Reattach guards for Port and STBD engines
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
04 - Emergency Systems › N/A - No Subsystem › Location of emergency installations
Issued 31 October 2019 Resolved
Affix Label “Fire Extinguisher” in STBD companionway for portable fire extinguisher, fire extinguisher is not clearly visible
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 31 October 2019 Resolved
Exposed electrical wire at base of mast is a tripping hazard, readjust length or secure wire so it is no longer a hazard
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
04 - Emergency Systems › N/A - No Subsystem › Water level indicator
Issued 31 October 2019 Resolved
Label each bilge high level indicator at operating station
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
09 - Working and Living Conditions › 092 - Working Conditions › Guards - fencing around dangerous machinery parts
Issued 31 October 2019 Resolved
Add lagging (insulation) to Port and STBD engine exhaust pipes up to point where water cooling injection fitting is located
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
05 - Radio Communications › N/A - No Subsystem › Other (radio communication)
Issued 31 October 2019 Resolved
Provide VHF emergency broadcast placard at the operating station
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
05 - Radio Communications › N/A - No Subsystem › Other (radio communication)
Issued 31 October 2019 Resolved
Demonstrate proper operation of installed public address system
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 31 October 2019 Resolved
Vessel over 65ft shall have a sound producing device audible up to 1 NM
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 10 December 2019
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 31 October 2019 Resolved
Post all pages of COI (3)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 31 October 2019 Resolved
All inspections listed in vessels rigging preventative maintenance program shall be logged and made available to USCG upon request (weekly, monthly, quarterly, biannually)
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 10 December 2019
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 31 October 2019 Resolved
Post sign on fuel tank compartment door just aft of engine room on both Port and STBD sides stating the following “KEEP DOOR CLOSED WHEN NOT OCCUPIED, FIXED FIRE EXTINGUISHING SYSTEM ONLY CAPABLE OF PROTECTING ENGINE ROOM SPACE”; Letters must be at least 1 inch
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 November 2019
Resolved 10 December 2019
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 31 October 2019 Resolved
Portable/temporary cord used to power main fridge in bar area does meet requirements set forth in the National Electric Code. Permanent receptacle installation required, submit plans to include materials to local OCMI prior to start of installation.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 10 December 2019
11 - Life Saving Appliances › N/A - No Subsystem › Operational readiness of lifesaving appliances
Issued 20 September 2019 Resolved
Provide plan to USCG for alternative stowage location for adult PFD's so that they are readily available in the event of an emergency. Currently PFD's are stowed under main deck in forward watertight hatches.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 17 October 2019
Resolution: PFD's stowed back in main compartment on both Port and STBD sides.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 20 September 2019 Resolved
Demonstrate proper operation of Fireboy visual indicators at operating station. When tested both Port and STBD indicators were audible and engines shut down, LED indicator for discharging did not illuminate.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 17 October 2019
Resolution: Indicators replaced at op station, tested satisfactory.
10 - Safety of Navigation › N/A - No Subsystem › Radar
Issued 20 September 2019 Resolved
Demonstrate proper operation of installed marine radar, vessel is restricted from voyages with reduced visibility. Capitan shall verify weather prior to departure.
Action required: 705 - Other - as specified
Resolved 17 October 2019
Resolution: Tested radar, all sat.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 9 September 2019 Resolved
Deficiency # 01 on CG-835 dated 09/05/2019 is cl;eared as visual inspection was completed. Corrosion was found on the embedded steel of the forward port hull attachment point. This, coupled with a crack found on the port aft chain plate, constitutes a necessity for an independent (third party) professional rigging survey to be completed on the vessel. Vessel is authorized to be placed in the water to conduct rigging survey if required by surveyor. Ensure survey is completed and report is submitted to local OCMI to verify safety of rig prior to operating with passengers.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 September 2019
Resolution: Report from Metalurgist, see attached report.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 4 September 2019 Resolved
Grind down identified/marked cracks on Port/STBD forward upper shrouds. Make areas available for re-inspection by attending Marine Inspector. Provide repair proposal for any laminate that is compromised with cracks.
Action required: 705 - Other - as specified
Resolved 9 September 2019
Resolution: Issued additional guidance for deficiency.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 4 September 2019 Resolved
Replace Port and STBD cutlass bearings.
Action required: 705 - Other - as specified
Resolved 17 September 2019
Resolution: Cutlass replaced
02 - Structural Conditions › N/A - No Subsystem › Hull - cracking
Issued 4 September 2019 Resolved
Repair identified areas on hull; (STBD bow, Port/STBD keels in way of props, STBD transom)
Action required: 705 - Other - as specified
Resolved 17 September 2019
Resolution: Identified areas repaired.
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 4 September 2019 Resolved
Deck rails must be installed near the periphery of all decks of a vessel accessible to passengers. Rail courses must be at 4" intervals for excursion vessels.
Action required: 705 - Other - as specified
Resolved 19 September 2019
Resolution: Rail courses re-installed and at required intervals.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 4 September 2019 Resolved
Make all penetrations in Port/STBD watertight bulkheads watertight on both sides of bulk heads in way of wiring runs.
Action required: 705 - Other - as specified
Resolved 20 September 2019
Resolution: All wire runs have been sealed at WTB's.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 4 September 2019 Resolved
Provide metal supports spaced no more than 24 inches for all vessels wiring and in such a manner to avoid chaffing. Plastic tie wraps are not to be used for supporting wires.
Action required: 705 - Other - as specified
Resolved 20 September 2019
Resolution: Wiring and supports installed.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 4 September 2019 Resolved
Remove any dead end wires or wires no longer in use.
Action required: 705 - Other - as specified
Resolved 20 September 2019
Resolution: Removed.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Scuppers, inlets and discharges
Issued 4 September 2019 Resolved
Replace bilge piping for submersible bilge pumps with piping of substantial construction (crush resistant)and provide positive shutoff valve at hull penetration.
Action required: 705 - Other - as specified
Resolved 19 September 2019
Resolution: All bilge piping and shutoff valves installed.
02 - Structural Conditions › N/A - No Subsystem › Decks - cracking
Issued 4 September 2019 Resolved
Repair deck area in way of embarkation area on Portside.
Action required: 705 - Other - as specified
Resolved 17 September 2019
Resolution: Deck repaired.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 16 April 2019 Resolved
A vessel over 65ft in length must be provided with 2 fixed power bilge pumps that are driven off different power sources. A catamaran vessel must be equipped with bilge pumps for each hull as if each hull is a separate vessel except where: the bilge system is permanently cross connected between hulls. Cross connect bilge system with piping not less than 1.5 inches in normal size and same material (ferrous) as existing fixed bilge system. Piping shall be labeled at manifold on both hulls. **Complete by credit drydock; Drydock due by November 30th, 2019.
Action required: 705 - Other - as specified
Due 30 November 2019
Resolved 30 April 2019
Resolution: Issued requirement of repairs to be made by next scheduled drydock.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 8 January 2019 Resolved
A vessel over 65ft in length must be provided with 2 fixed power bilge pumps that are driven off different power sources. A catamaran vessel must be equipped with bilge pumps for each hull as if each hull is a separate vessel except where: the bilge system is permanently cross connected between hulls. Submit plans to the local OCMI prior to any installations or changes in current arrangement.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 17 April 2019
Resolution: Issued requirement to complete by next credit drydock.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Scuppers, inlets and discharges
Issued 8 January 2019 Resolved
Provide adequate bilge suction for draining all watertight compartments, space forward of the collision bulkhead need not be fitted with a bilge suction line and may be accomplished by use of hand portable bilge pump or other equipment.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: Pump provided to dewater compartment forward of collision bulkhead.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 8 January 2019 Resolved
Repair/replace indicated section of bilge piping on STBD side for forward compartment.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 24 January 2019
Resolution: Piping replaced in kind.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 8 January 2019 Resolved
Provide shutoff valves at the fuel tank connection for both Port and STBD installations. Valve must be manually operable from outside the space, preferably from the weather deck.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 24 January 2019
Resolution: Fuel shutoffs added to fuel tank connection.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 8 January 2019 Resolved
Provide access to compartment for inspection forward of collision bulkhead on both Port and STBD hulls.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: 8inch access panels added to Port/STBB collision bulkheads.
11 - Life Saving Appliances › N/A - No Subsystem › Lifeboats
Issued 8 January 2019 Resolved
One of the Three Life floats was faded, repaint with international orange ([name withheld]) paint.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 24 January 2019
Resolution: Life Floats repainted.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 8 January 2019 Resolved
Replace stainless lower shroud on port side, should was bent near toggle.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 24 January 2019
Resolution: Shroud replaced in kind.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 8 January 2019 Resolved
Provide over-current protection device to all wires connected directly to battery terminal within 72 inches of wire run to battery terminal.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: Overcurrent protection installed.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 8 January 2019 Resolved
All connections to battery terminals shall be made with permanent type connectors, wing nuts are not permanent type.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: Wing nuts removed and lock nuts added.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 8 January 2019 Resolved
Ensure that only 4 wire connections are allowed per battery terminal.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: Wires removed.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 8 January 2019 Resolved
Wires may not be spliced with twist type connectors to extend the length of a circuit. STBD fuel tank space, raw water wash pump.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: Spice made with pressure fitting.
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 8 January 2019 Resolved
Make available a Rigging Preventative Maintenance Program that provides a level of detail commensurate with Appendix (2) to Enclosure (1) of NVIC 02-16 (Rigging Inventory/Preventative Maintenance Inspection Template (Sample)) or propose a mutually acceptable third party to survey the rigging and provide a report with a level of detailed commensurate with either Appendix (3) or (4) to Enclosure (1) of NVIC 02-16 (Third Party Rigging Survey Samples A&B).
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 12 February 2019
Resolution: PMP received.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 8 January 2019 Resolved
Replace floating waterlight batteries. (04 total)
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 January 2019
Resolution: Batteries replaced.
Fire Fighting › Fire Pumps › Capacity
Issued 16 January 2018 Resolved
Renew/replace fire pump. Must be capable of 50 GPM at a pressure of not less than 60 psi at pump outlet.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 29 January 2018
Resolution: pump reached 60 psi and adequate stream
Electrical › Electric Supply System (service) › Cable
Issued 16 January 2018 Resolved
Renew chaffed electrical cable in STBD hull by chain plate. Install chaffing gear to prevent reoccurrence.
Action required: 705 - Other - as specified
Due 23 January 2018
Resolved 29 January 2018
Resolution: chaffing gear applied
Stability › Watertight Integrity › General
Issued 16 January 2018 Resolved
Make port collision bulkhead watertight. Penetration on watertight bulkhead.
Action required: 705 - Other - as specified
Due 23 January 2018
Resolved 29 January 2018
Resolution: penetration in bulkhead sealed.
Fire Fighting › Fire Pumps › Arrangement
Issued 16 January 2018 Resolved
Make available means to remotely operate fire pump from operating station.
Action required: 705 - Other - as specified
Due 16 February 2018
Resolved 29 January 2018
Resolution: remote location under the STBD stairs provided, special note added.
Lifesaving › Lifefloat › Serviceable
Issued 16 January 2018 Resolved
Renew/repair life floats IAW manufacture instructions. Vessel restricted to 3nm from land.
Action required: 705 - Other - as specified
Due 16 February 2018
Resolved 10 April 2018
Resolution: New life floats onboard and properly outfitted/connected.
Lifesaving › Lifejacket/PFD (General) › Condition
Issued 16 January 2018 Resolved
Service all PFD's to be capable for immediate use.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 29 January 2018
Resolution: All PFD's serviceable
Lifesaving › Lifebuoys › Serviceable
Issued 16 January 2018 Resolved
Renew/replace 01 ring buoy
Action required: 705 - Other - as specified
Due 23 January 2018
Resolved 29 January 2018
Resolution: new buoy provided
Navigation › Piloting/Steering › Magnetic Compass
Issued 16 January 2018 Resolved
Provide light for magnetic compass
Action required: 705 - Other - as specified
Due 23 January 2018
Resolved 29 January 2018
Resolution: new compass installed
Navigation › Piloting/Steering › Coast Guard Light List
Issued 16 January 2018 Resolved
Provide all required publications IAW 46CFR184.420.,
Action required: 705 - Other - as specified
Due 23 January 2018
Resolved 29 January 2018
Resolution: publications printed out and supplied.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 16 January 2018 Resolved
Provide watertight container for first aid kit.
Action required: 705 - Other - as specified
Due 23 January 2018
Resolved 5 February 2018
Resolution: Watertight container provided.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Condition
Issued 16 January 2018 Resolved
Renew/replace 01 B-II portable fire extinguisher.
Action required: 705 - Other - as specified
Due 16 February 2018
Resolved 29 January 2018
Resolution: new B-II extinguisher onboard
Fire Fighting › Fire Hoses › Connections
Issued 16 January 2018 Resolved
Provide spanner wrench for fire station.
Action required: 705 - Other - as specified
Due 16 February 2018
Resolved 29 January 2018
Resolution: wrench provided at fire hydrant.
Operations/Management › Navigation Safety › Navigation Underway, General
Issued 14 November 2017 Resolved
Conduct an operational test and sea trails of the rigging prior to carrying passengers under sail as described in NVIC 02-16.
Action required: 701 - Prior to carriage of passengers/cargo
Due 15 December 2017
Resolved 18 December 2017
Resolution: Operational Test Conducted
Sail Rigging › Chainplates › Materials
Issued 16 October 2017 Resolved
Fond chain plate bolts to be wasted. Remove chain plates for inspection. Repair & replace unserviceable items.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 16 October 2017
Resolved 15 November 2017
Resolution: New hardware installed. All sat.
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 16 October 2017 Resolved
Make welding repairs to the cracks on inboard aluminum handrails on port side IAW 46 CXFR 177.900.
Action required: 705 - Other - as specified
Due 15 December 2017
Resolved 18 December 2017
Resolution: Cracks repaired
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 15 December 2016 Resolved
Prove proper operation of port fireboy engine shutdown and override
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 15 December 2016
Resolution: Fixed bad connection
Fire Fighting › Fire Pumps › Pressure
Issued 15 December 2016 Resolved
Prove proper operation of fire pump
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 15 December 2016
Resolution: Rebuilt fire pump
Engineering › Bilge Water Management System › Valve
Issued 15 December 2016 Resolved
Install check or stop check valves in individual suction lines
Action required: 705 - Other - as specified
Due 15 January 2017
Resolved 17 January 2017
Resolution: Installed check valves in all suction lines.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 15 December 2016 Resolved
Install guards on front of engines
Action required: 705 - Other - as specified
Due 15 January 2017
Resolved 17 January 2017
Resolution: Installed guards on both engines
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 15 December 2016 Resolved
Make repairs to starboard deck rail stanchion sockets
Action required: 705 - Other - as specified
Due 15 January 2017
Resolved 17 January 2017
Resolution: Made repairs to stanchions
Lifesaving › Lifefloat › Serviceable
Issued 15 December 2016 Resolved
Make repairs to lifefloat in accordance with manufacture's instructions
Action required: 705 - Other - as specified
Due 15 January 2017
Resolved 17 January 2017
Resolution: Repaired life floats
Engineering › Fuel Oil Service System › Tank
Issued 15 December 2016 Resolved
Renew fuel tanks with tanks that meet requirements of 46 CFR 182.440
Action required: 705 - Other - as specified
Due 29 October 2017
Resolved 26 October 2017
Resolution: Fuel tanks replaced.
Engineering › Fuel Oil Service System › Tank
Issued 15 December 2016 Resolved
Electrically bond fuel tanks to a common ground
Action required: 705 - Other - as specified
Due 15 January 2017
Resolved 17 January 2017
Resolution: Bonded fuel tanks to common ground
Communications › Radio Communications › VHF Radiotelephone
Issued 15 December 2016 Resolved
Connect VHF-DSC to GPS input
Action required: 705 - Other - as specified
Due 15 January 2017
Resolved 17 January 2017
Resolution: Connected radio to GPS
Documentation › Markings/Placards › Garbage Placard
Issued 21 January 2016 Resolved
Vessel did not have garbage placard or waste management plan as required.
Action required: 705 - Other - as specified
Due 21 February 2016
Resolved 21 January 2016
Resolution: Placard and plan were provided prior to the completion of the inspection
Fire Fighting › Fire Hoses › Condition
Issued 21 January 2016 Resolved
Found that the only fire hose on board had multiple holes in it.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 21 January 2016
Resolved 21 January 2016
Resolution: Hose replaced prior to the completion of the inspection
Fire Fighting › Fire Pumps › Pressure
Issued 21 January 2016 Resolved
Found that fire pump did not put out required 60 psi during first test.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 21 January 2016
Resolved 21 January 2016
Resolution: With new hose, pump supplied adequate pressure after getting underway. Suspect that seaweed may have been caught in intake.
Communications › Alarms/Indicators › Bilge Alarm
Issued 21 January 2016 Resolved
Vessel's bilge high water alarms were not sounding adequately at the operating station
Action required: 705 - Other - as specified
Due 27 January 2016
Resolved 25 January 2016
Resolution: Vessel alarms replaced, shown that they properly operate.

Casualty record · 10

17 March 2006Routine · role: Transiting Vicinity of Primary Subject · serious marine incident, as classified · 1 dead · activity 2604364
24 March 2011Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 3971301
22 August 2011Routine · role: Involved in a Marine Casualty · activity 4124999
26 October 2011Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 dead · activity 4176702
6 April 2012Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 4285517
25 December 2019Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 6879660
20 September 2020Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 dead · activity 7067909
29 September 2020Routine · role: Involved in a Marine Casualty · activity 7067879
24 October 2020Routine · role: Involved in a Marine Casualty · 1 injured · activity 7084098
24 April 2021Routine · role: Involved in a Marine Casualty · 1 injured · activity 7182958
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.

Recorded names · 1

SEBAGO MARQUESA (2019). Names as the Coast Guard recorded them in incident records, with the years they appear; some are renames and some are spelling variants.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.