Inspection history · 55
22 March 2010
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3725406
3 February 2009
Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3428062
31 January 2008
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3149620
7 January 2008
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3126031
19 November 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3100820
20 July 2007
Deficiency Check
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3001614
22 June 2007
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2970142
22 June 2007
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2981954
1 March 2007
Periodic Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2886471
23 March 2006
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2616746
12 April 2005
Internal Structural Exam · Examination of Repairs · Deficiency Check · MTSA Verification · COI Inspection
Physical examination · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 2332208
28 April 2004
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2080210
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1988536
1 December 2003
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1956622
21 July 2003
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1900531
20 January 2003
Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1738067
11 June 2002
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1629750
30 January 2002
Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1482800
5 September 2001
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 216533
5 September 2001
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 470237
30 July 2001
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1069351
17 June 2001
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 95025
12 February 2001
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1058149
20 March 2000
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 817488
20 March 2000
Hull Examination
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1455830
3 February 1999
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 799721
21 January 1998
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 778697
6 March 1997
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1101253
29 January 1997
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 96835
29 January 1997
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 179356
22 February 1996
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 885547
20 March 1995
Hull Examination · COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1167934
17 February 1994
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 853049
11 February 1994
COI Inspection
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1366972
8 March 1993
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1391822
2 July 1992
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1264085
11 February 1992
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1134283
12 March 1991
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 929934
28 March 1990
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1214665
23 March 1990
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 909846
22 March 1990
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 928633
16 February 1990
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 924829
4 November 1988
Hull Examination · COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 891032
18 July 1988
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1340417
17 July 1987
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1023567
24 September 1986
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 458047
27 August 1986
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1319436
3 April 1986
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 526443
8 March 1986
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 494467
23 July 1985
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1291871
14 February 1985
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 300412
10 February 1985
Type not recorded
No type recorded · COTP HOUSTON · USCG Heartland District (CGD-H) · Activity 526367
30 July 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1282922
21 July 1983
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 964959
11 August 1981
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1275725
Construction/Loadline › Hull › Hull Plating
Issued 19 November 2007
Resolved
Vessel reports fracture in port stern corner in the weld seam at they transom lap at the 7' draft mark
Condition: Unknown
Action required: 705 - Other - as specified
Due 30 December 2007
Resolved 30 December 2007
Resolution: Tbsip report recived G/W 24" fracture on port stern void on cornerand transom lap 2 7'' draft mark.
Construction/Loadline › Hull › Hull Plating
Issued 22 June 2007
Resolved
Provide repair proposal and make permanent repairs to damage on the starboard bow.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 20 July 2007
Resolution: Repair proposal received and permanent repair made to stbd bow deck and rake.
Deck/Cargo
Issued 11 February 1994
Resolved
The cargo system level alarms must be tested._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 11 February 1994
Resolved 11 February 1994
Deck/Cargo
Issued 11 February 1994
Resolved
The Vapor Recovery System must be tested and made available for inspection._x001C_
Condition: Unknown
Due 11 February 1994
Resolved 11 February 1994
Deck/Cargo
Issued 11 February 1994
Resolved
The cargo Transfer piping system must be hydro tested to 1.5 mawp._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 11 February 1994
Resolved 11 February 1994
Deck/Cargo
Issued 11 February 1994
Resolved
The Cargo Vent System pressure-vacuum valve must be tested and inspected._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 11 February 1994
Resolved 11 February 1994
Deck/Cargo
Issued 11 February 1994
Resolved
The cargo system prime mover emergency shutdown must be repaired and testedprior to cargo operations._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 11 February 1994
Resolved 11 February 1994
Construction/Loadline
Issued 23 March 1990
Resolved
MAKE FWD RAKE AVAILABLE FOR INSPECTION.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Unknown
Issued 22 March 1990
Resolved
MAKE PERMANENT REPAIRS TO 7 INCH FRACTURE IN HEAD LOG IN WAY OF STBD PUSHER KNEE, AND MAKE A PERMANENT REPAIRS TO PUSHER KNEE.
Condition: Unknown
Due 22 March 1990
Resolved 22 March 1990