Records from 2005 to 2025. Most recent: inspection, 23 October 2025.
Documentation record
Registered dimensions (L × B × D)200.0 ft × 35.0 ft × 12.5 ft
Registered tonnagegross 735 / net 735
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderJEFFBOAT LLC · JEFFERSONVILLE, IN, UNITED STATES · built 2005
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portNEW ORLEANS, LA
Trade endorsementsCoastwise, unrestricted, Registry, non-fishing vessel
DocumentationValid · issued 25 September 2025 · expires 30 September 2026
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it735 - Simplified, Gross Ton
735 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 30
23 October 2025
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8257664
28 April 2025
MTSA Verification · Cargo Tank Internal · Drydock Exam · COI Inspection · Examination of Repairs · Internal Structural Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8112647
24 May 2024
Type not recorded
No type recorded · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 7918127
23 August 2022
Damage Survey · Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7541136
18 November 2021
Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 7353603
6 April 2020
MTSA Verification · COI Inspection · Internal Structural Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6930584
1 September 2017
Annual Inspection · Administrative Inspection · Damage Survey · COI Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6260003
26 January 2017
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6077653
1 December 2016
Examination of Repairs · Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6050776
24 November 2016
Type not recorded
No type recorded · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6047366
24 November 2016
Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6047389
4 August 2016
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5959631
23 April 2015
Deficiency Check · Cargo Tank Internal · Drydock Exam · MTSA Verification · COI Inspection · Internal Structural Exam · Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5104032
11 March 2015
Administrative Inspection · Permit to Proceed · Damage Survey
Physical examination · Sector Lower Mississippi · USCG Heartland District (CGD-H) · Activity 5082059
10 March 2015
Type not recorded
No type recorded · Sector Lower Mississippi · USCG Heartland District (CGD-H) · Activity 5106751
25 April 2014
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4837316
10 July 2013
Examination of Repairs
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 4650038
11 April 2012
MTSA Verification · Periodic Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4284753
1 June 2011
Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 4030189
3 May 2010
Internal Structural Exam · COI Inspection · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3725315
16 July 2009
Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3535455
16 June 2009
Deficiency Check · Administrative Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3505839
29 May 2009
Damage Survey · Permit to Proceed
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 3494213
28 May 2009
Type not recorded
No type recorded · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 3489218
5 May 2009
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3473962
7 May 2008
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3201654
16 March 2007
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2889148
15 June 2006
Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2680516
25 May 2005
Internal Structural Exam · Initial Certification · MTSA Verification · Hull Examination · Cargo Tank Internal
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 2367683
9 February 2005
Security Plan Amendment Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 2289467
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 23 August 2022
Resolved
Cargo hose shall not be used in transfer operations in which the pressures are such that leakage of cargo occurs through the body of the hose. vessel sustained a half an inch crack on the weld for the 2" bypass line after the check valve causing a half of a cup of ethanol to spill onto the deck. Prior to the handling of future cargo operations, permit repairs must be made to me satisfaction of the Coast Guard.
46 CFR 35.35-70(a)
Action required: 701 - Prior to carriage of passengers/cargo
Due 23 August 2022
Resolved 30 August 2022
Resolution: Marine inspector visually inspected welds and tested cargo stripping line at 198 PSI, all tests sat.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 5 September 2017
Resolved
Vessel failed to have its Annual Inspection completed within the 180 day (6 month) window of its 03 June anniversary date. 46 CFR 31.10-17
Condition: Invalid
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 September 2017
Resolved 11 September 2017
Resolution: Passed inspection, issued new COI.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 1 September 2017
Resolved
Vessel failed to maintain a valid COI by not completing your annual inspection. Therefore your COI is invalid and you must submit a written application for an inspection for certification for new COI. 46 CFR 31.10-17a
Condition: Invalid
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 September 2017
Resolved 11 September 2017
Resolution: Passed inspection, issued new COI.
Construction/Loadline › Hull › Hull Plating
Issued 11 March 2015
Resolved
Port side bilge knuckle of bow rake, approx 5' above waterline a hole that was approx. 4-5" in length and set in approx 1.5-2" was discovered. Possibly from running up on a timberhead on a loaded barge in the fleeting area or when being placed in the tow.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 April 2015
Resolution: Cropped and renewed damaged areas. Attending marine inspector witnessed sat air test and visual inspection of the welds.
Stability › Unintentional Flooding › General
Issued 29 May 2009
Resolved
Hull fracture(s) to #4 starboard wing void at bilge knuckle and into bottom plate 3' below waterline. Provide repair proposal to cognizant OCMI and effect permanent repairs to the satisfaction of attending CG MI.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 16 July 2009
Resolution: Inserts to side shell, bilge knuckle. Witness sat air test.
Stability › Watertight Integrity › General
Issued 29 May 2009
Resolved
Hull fractures 3' above waterline in #3 starboard wing void. Provide repair proposal to cognizant OCMI and effect permanent repairs to the satisfaction of attending CG MI.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 16 July 2009
Resolution: Inserts to side shell, bilge knuckle, bottom plate. Witnessed sat air test.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 29 May 2009
Resolved
Starboard tank wall IWO #3 & #4 wing voids inset approximately 2", cargo envelope intact (tight). Make ready for examine (ISE/CTIE) by CG MI to determine repair proposal ID'd all effected areas and required repair(s).
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 16 July 2009