Records from 2007 to 2026. Most recent: inspection, 20 August 2026.
Documentation record
Registered dimensions (L × B × D)408.0 ft × 78.0 ft × 34.5 ft
Registered tonnagegross 6,310 / net 6,310
ITC dimensions (L × B × D)408.0 ft × 78.0 ft × 34.5 ft
ITC tonnagegross 8,460 / net 5,432
BuilderMANITOWOC MARINE GROUP · STURGEON BAY, WI, UNITED STATES · built 2007
Hull materialSteel
PropulsionNot recorded
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portWILMINGTON, DE
Trade endorsementsCoastwise, unrestricted, Registry
DocumentationValid · issued 5 February 2026 · expires 31 March 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it8460 - Convention (Subpart B), Gross Ton
6310 - Regulatory (Subpart C or D), Gross Ton
5432 - Convention (Subpart B), Net Ton
6310 - Regulatory (Subpart C or D), Net Ton
18406 - Dead Weight, Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 37
20 August 2026
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 8468812
6 July 2026
Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 8430665
27 May 2026
Administrative Inspection · MTSA Verification · Deficiency Check · Annual Inspection
Physical examination · Sector Jacksonville · USCG Southeast District (CGD-SE) · Activity 8403094
11 March 2026
Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8324566
14 February 2026
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8310808
6 February 2026
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8307216
8 November 2025
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8266090
21 October 2025
Damage Survey · Administrative Inspection
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 8256180
16 January 2025
Examination of Repairs · Internal Structural Exam · Drydock Exam · Periodic Inspection · Administrative Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8064686
23 September 2024
Deficiency Check · Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 8008389
12 June 2024
Administrative Inspection · Annual Inspection · Deficiency Check
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7933550
5 January 2023
Annual Inspection · Administrative Inspection · Deficiency Check · Examination of Repairs · Internal Structural Exam · In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7614846
16 November 2021
MTSA Verification · Administrative Inspection · In-Service Inspection · COI Inspection · Internal Structural Exam · Examination of Repairs
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7351159
7 October 2021
Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 7328489
22 July 2021
Administrative Inspection
Administrative · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7265167
10 November 2020
Deficiency Check · Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7084936
27 May 2020
Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 6961601
18 November 2019
MTSA/ISPS Verification · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6857934
8 October 2019
Drydock Exam · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6830372
19 May 2019
Bulk Liquid Transfer Monitor
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6687787
1 November 2018
Periodic Inspection · Administrative Inspection · MTSA Verification
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6572716
1 November 2017
MTSA Verification · Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6298413
18 August 2016
Cargo Tank Internal · COI Inspection · Administrative Inspection · Examination of Repairs · Drydock Exam · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 5976003
15 June 2015
Hull Examination · Deficiency Check · Periodic Inspection · MARPOL Annex I Examination · MTSA Verification · Examination of Repairs · Administrative Inspection · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 5153943
23 January 2014
MARPOL Annex VI Survey · MARPOL Annex I Examination · Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4783979
19 July 2012
Administrative Inspection · Internal Structural Exam · COI Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4469500
10 May 2012
MARPOL Annex VI Survey
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4307428
22 December 2011
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 4219123
23 November 2011
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4193780
6 January 2011
Periodic Inspection · MARPOL Annex VI Survey · MARPOL Annex I Examination · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3921816
10 June 2010
Administrative Inspection · Internal Structural Exam · MARPOL Annex VI Survey · MARPOL Annex I Examination · Drydock Exam · Examination of Repairs
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3762748
21 January 2009
Annual Inspection · MARPOL Annex V Examination · MTSA Verification · MARPOL Annex I Examination · Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3397459
14 January 2009
Type not recorded
No type recorded · Marine Safety Unit Coram · USCG Northeast District (CGD-NE) · Activity 3395630
9 January 2009
Type not recorded
No type recorded · Sector Boston · USCG Northeast District (CGD-NE) · Activity 3392515
11 September 2008
Type not recorded
No type recorded · Marine Safety Unit Coram · USCG Northeast District (CGD-NE) · Activity 3325467
9 January 2008
Deficiency Check · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3127233
16 November 2007
Initial Certification · Cargo Tank Internal · Internal Structural Exam · Construction Oversight · Hull Examination
Physical examination · Marine Safety Unit Sturgeon Bay · USCG Great Lakes District (CGD-GL) · Activity 3091856
14 - Pollution Prevention › 148 - Ballast Water › Ballast Water Management System (BMWS)
Issued 6 July 2026
Resolved
The master of each vessel subject to this subpart shall employ one of the required ballast water management practices.
The vessel is experiencing a failure of the ballast water system on the 3S, 4S, and 5S ballast tanks that is causing the starboard ballast pump to lose suction as the tanks are being pumped out, preventing the water from being sent through the onboard ballast water treatment system.
Determine the cause of the failure and conduct repairs to the ballast water system prior to discharging untreated ballast water.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 6 July 2026
Resolved 5 August 2026
Resolution: Shipyard identified leaks and applied doublers to piping system.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 14 February 2026
Resolved
Unless otherwise expressly provided for in this subpart, the master, owner, operator, agent, or person in charge of vessels employing a Coast Guard-approved BWMS must meet the applicable ballast water discharge standard (BWDS), found in § 151.2030 of this subpart, at all times of discharge into the waters of the United States.
Vessel reported alarm on their STBD BWTS "UV Chamber Moisture Detected" and is unable to timely repair due to specific part shortage.
Vessel is authorized a one time discharge of ballast water in New Orleans to conduct cargo operations and is then restricted from discharging untreated ballast water in U.S. waters until permanent repairs are completed and a technician report attesting to satisfactory repair of the BWTS to Coast Guard Marine Inspectors.
Action required: 705 - Other - as specified
Resolved 24 February 2026
Resolution: Received tech report stating STBD BWT System is repaired. Issued new deficiency restricting use of PORT BWT system until technicians repair report is received.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 12 June 2024
Resolved
Each pressure gauge must show pressure within 10 percent of the actual pressure; The #2 cargo pump gauge was reading 60-70 psi over the actual pressure in pipe. 33 CFR 156.170(c)(3)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 26 June 2024
Resolved 24 June 2024
Resolution: MI recieved photo of new gauge installed.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 12 June 2024
Resolved
Electric installations on vessels must ensure:(1) Maintenance of services necessary for safety under normal and emergency conditions. The ground detector on the 120v panel in the stbd pump room was indicating a ground fault on the 3rd phase indicator. Notify CG cause of ground fault and repair in kind.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 26 June 2024
Resolved 24 June 2024
Resolution: Ground was caused by a portable lighting fixture from the 120V distribution system. Light fixture was disgarded. Ground Indication System is back to normal function.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 10 November 2020
Resolved
Flexible non-metallic hose shall be suitable for installation. Abrasions were observed on multiple fuel oil non-metallic hoses on the #1 and #2 diesel generators. Add chafe gear to fuel oil hoses.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 24 November 2020
Resolved 12 November 2020
Resolution: Received pictures of chafe gear installed on hoses.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 10 November 2020
Resolved
All electrical installations in hazardous areas shall meet the appropriate standard. The #2 port ballast tank level sensor housing cover was damaged, compromising its integrity and suitability for installation.
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 24 November 2020
Resolved 12 November 2020
Resolution: Received video showing the cover properly bolted down, resotring housing's integrity
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 10 November 2020
Resolved
Each vapor connection flange must have a permanent stud projecting outward. The port manifold vapor line flange was missing the preventer stud.
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Resolved 10 November 2020
Deck/Cargo › Ballast › Tank
Issued 20 September 2016
Resolved
Submit repair proposal and repair buckling identified in #2 port ballast tank swash bulkhead IAW 46 CFR 31.10-21(c).
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 September 2016
Resolution: Repaired buckling identified in swash bulkhead.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 20 September 2016
Resolved
Submit repair proposal and repair crack identified in #5 stbd cargo tank IAW 46 CFR 31.10-21(c).
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 21 September 2016
Resolution: Repaired crack in cargo tank.
Deck/Cargo › Ballast › Segregated Ballast Tank
Issued 15 June 2015
Resolved
Crop out and renew inset (40" x 60"), located on swash bulkhead/Frame #31.
Action required: 705 - Other - as specified