LILY BLAIR is a 2009 tank barge. The Coast Guard has recorded 29 inspections since 2009, most recently in April 2026, along with 9 deficiencies and 2 casualty investigations between 2013 and 2018.
Records from 2009 to 2026. Most recent: inspection, 29 April 2026.
Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Barge class in Maury's sources begin in 1972.
Every line above is a count of records the US Coast Guard wrote, or a date it recorded.
A blank resolution means none was recorded in this data; it does not establish that a
deficiency is outstanding. Years with a record are calendar years in which a record
exists, not years in service. What Maury does
not do.
DocumentationValid · issued 18 February 2026 · expires 31 March 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it2724 - Convention (Subpart B), Gross Ton 1403 - Convention (Subpart B), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Vessel history report
Every record for this hull, in one document — $299
Every recorded inspection, 1972 to
2026 for this class, in one chronology · every deficiency, with system, dates
and resolution · operational controls imposed and removed · every name this
hull has been recorded under · the vessels it was inspected alongside, and when
· how its record compares with hulls of similar age and size, as a fact about the
population and never a judgement about this vessel.
This report is in development and is not for sale yet. There is
no date, and nothing is charged. Leave an email and we will tell you when it exists, once.
Used only to tell you when the report exists.
Not shared, not sold, and not added to a mailing list.
Inspection history · 29
29 April 2026Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8309561
6 May 2025MARPOL Annex VI Survey · MARPOL Annex I Examination · Periodic Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8076468
2 May 2024Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7895583
8 April 2024Drydock Exam
Physical examination · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 7892773
27 March 2024Drydock Extension · Internal Structural Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7884571
3 April 2023Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7635224
1 March 2022Internal Structural Exam · COI Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7397363
6 May 2021Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7190972
27 May 2020MTSA/ISPS Verification · Periodic Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6919245
28 June 2019MARPOL Annex VI Survey · MARPOL Annex I Examination
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6726819
25 April 2019Drydock Exam · Administrative Inspection · Cargo Tank Internal · Deficiency Check
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 6669777
11 February 2019Internal Structural Exam · Drydock Extension · Administrative Inspection · Annual Inspection · Cargo Tank Internal
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6611261
19 April 2018Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6360687
29 January 2018Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6345844
1 March 2017COI Inspection · Internal Structural Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6083590
12 August 2016Deficiency Check · Periodic Inspection · MTSA Verification
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5970545
10 June 2015Annual Inspection · MTSA Verification
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5113474
3 March 2014Drydock Exam · Internal Structural Exam · COI Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 4809091
4 June 2013Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 4579502
7 July 2012Type not recorded
No type recorded · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 4370979
27 May 2012Type not recorded
No type recorded · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 4324087
8 May 2012Internal Structural Exam · Annual Inspection
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 6 May 2025Resolved
A fixed cargo piping system shall be installed on a tank vessel carrying Grade A, B, or C cargo. The piping shall be arranged so as to avoid excessive stresses at the joints. For sizes exceeding 2 inches in diameter, flanged, welded, or other approved types of joints shall be employed. Packing material shall be suitable for the cargo carried. Connections at bulkheads shall be made so that the plating does not form part of a flanged joint. Piping may be carried through bunker spaces and deep tanks provided it is run through a pipe tunnel. The tunnel may be omitted where the pipe is extra heavy, all joints are welded, and bends are installed to provide for expansion and contraction. MI observed threads weeping cargo from the port side cargo pump piping priming line. 46 CFR 32.50-15 (a)(1)
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 20 May 2025
Resolved 7 May 2025
Resolution: Priming line fitting has been re-tightened.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 11 February 2019Resolved
Missing non-rising stem valve indicators. Replace all non-rising stem valve indicators throught the barge.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 15 February 2019
Resolution: Replaced all missing indicators.
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 11 February 2019Resolved
Port and Starboard nav light were obstructed by railing. Ensure port and starboard nav light are unobstructed.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 March 2019
Resolved 15 February 2019
Resolution: Moved nav light to the outside of the hand rails. Lights are unobstructed.
Generator had excessive oil on windings. Clean oil residue off of the windings to the satisfaction of attending CG marine inspector.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 19 September 2016
Resolved 3 October 2016
Resolution: See Narrative.
Engineering › Diesel Engine (auxiliary) › Charge Air Cooling
Issued 12 August 2016Resolved
Remove excessive oil around radiator on both prime movers to the satisfaction of attending CG marine inspector.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 19 September 2016
Resolved 3 October 2016
Resolution: See Narrative.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 10 June 2015Resolved
Replace expired battery for lifebuoy waterlight.
Action required: 705 - Other - as specified
Resolved 10 June 2015
Resolution: corrected on the spot.
Valve position indicators on tanks 1P, 4S, and 4P are missing/inoperable. Vsl required to replace valve position indicators IAW 46 CFR 56.20-9.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 17 June 2010
Resolved 18 May 2010
Resolution: Repairs completed to the satisfaction of the attending Coast Guard Marine Inspector.
Fire Fighting › Portable CO2 Fire Extinguisher › Service
Issued 17 May 2010Resolved
Annual service not conducted for portable fire extinguishers. Vsl is required to provide annual servicing certificate for extinguishers.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 17 June 2010
Resolved 18 May 2010
Resolution: Sector Seattle received servicing certificate for extinguishers.
10 February 2013Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 4531820
29 January 2018Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 6345844
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.