Documentation record
Registered dimensions (L × B × D)86.7 ft × 22.7 ft × 9.3 ft
Registered tonnagegross 95 / net 65
ITC dimensions (L × B × D)86.7 ft × 22.7 ft × 9.3 ft
ITC tonnagegross 194 / net 67
BuilderWESTPORT SHIPYARD INC · WESTPORT WA, UNITED STATES · built 1996
Hull materialFRP (Fiberglass)
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portSEWARD, AK
Endorsements, as the file codes themcw_un, fi, reg
DocumentationValid · issued 11 February 2026 · expires 28 February 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it95 - Regulatory (Subpart C or D), Gross Ton
194 - Convention (Subpart B), Gross Ton
65 - Regulatory (Subpart C or D), Net Ton
67 - Convention (Subpart B), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Professional
The full record for this vessel
Behind this panel: 20 inspections, each with its date, unit and type; 18 deficiencies with the resolution recorded against each; operational controls, none recorded without a removal date; no tow-unit appearances recorded; no other recorded names; the documentation record: dimensions, tonnage, builder, hailing port and endorsements. Every line is a record the Coast
Guard wrote; the counts above are the same counts as in the summary, and they are free.
Professional is $39 a month or $299 a year,
or $19.99 a month locked for life at the founding rate, for the first 200 subscribers. It unlocks
every detail section on every vessel page, fleet watch tied to your account, and ownership records
on request. Already a subscriber? Sign in.
Maury does not score, rate or grade vessels, at any price.
Inspection history · 20
8 April 2026
COI Inspection · Administrative Inspection · Deficiency Check
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 8311178
2 October 2025
Drydock Exam · Internal Structural Exam
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 8245775
22 August 2025
Administrative Inspection · In-Service Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 8215498
17 April 2024
Annual Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 7897309
14 September 2023
Deficiency Check · Drydock Exam · Internal Structural Exam
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 7794200
4 May 2023
In-Service Inspection · Annual Inspection · Deficiency Check · Administrative Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 7680988
18 May 2022
Administrative Inspection · Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7454265
2 November 2021
Internal Structural Exam · Hull Examination · Deficiency Check · Administrative Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 7344025
29 April 2021
DAPI Audit · Administrative Inspection · COI Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 7186090
18 June 2020
Annual Inspection · DAPI Audit · Administrative Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 6980141
4 September 2019
Examination of Repairs · Drydock Exam · Deficiency Check · Internal Structural Exam
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6796577
28 May 2019
Annual Inspection
Physical examination · Detached Duty Office Seward · USCG Arctic District (CGD-A) · Activity 6697693
16 February 2018
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6356514
31 January 2018
Internal Structural Exam · Drydock Exam
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6342257
20 August 2017
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6247734
23 May 2017
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6094306
26 May 2016
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5909639
16 May 2016
Deficiency Check
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5907162
15 April 2016
Deficiency Check · COI Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5855299
20 January 2016
Deficiency Check · Internal Structural Exam · Hull Examination
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5797829
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 8 April 2026
Resolved
A device must be provided to automatically shut down power ventilation serving the protected space and engines that draw intake air from the protected space prior to release of the extinguishing agent into the space. Vessel's pressure switch for the main diesel engines did not shut down either main engine. 181.410(b)(10)
Condition: Design Flaw
Action required: 701 - Prior to carriage of passengers/cargo
Due 8 April 2026
Resolved 10 April 2026
Resolution: Vessel port engineer determined that the test of engine shutdown required a full reset of the MDE panel in order to reset the safety shut down. Retest sent via e-mail. All Sat.
14 - Pollution Prevention › 141 - MARPOL Annex I › Oil fuel tank protection
Issued 8 April 2026
Resolved
Remote fuel shutoff stations must be marked in clearly legible letters at least 25 millimeters (1 inch) high indicating purpose of the valve and direction of operation. Fuel oil shutoffs for the engines do not indicate the direction of operation or give instruction. 46 CFR 185.608
Condition: Placed in Improper Service
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 April 2026
Resolved 2 June 2026
01 - Certificates & Documentation › 013 - Documents › Stability Information Booklet
Issued 8 April 2026
Resolved
A vessel must be provided with a stability letter, the stability letter must be posted under glass or other suitable transparent material, such that all pages are visible, at the operating station of the vessel. If posting is impracticable, the stability letter must be kept on board in a weathertight container readily available for use by the crew and display to passengers and others on request. Vessel's stability letter on board was out-of-date and had been superseded by a newer stability letter dated 30DEC2014 referenced by the COI. 46 CFR 185.608
Condition: Damaged By Earlier Event
Action required: 10 - Deficiency Rectified
Resolved 8 April 2026
Resolution: Marine Inspector notified the vessel that the stability documentation was not recent and e-mailed the owner the current stability letter.
05 - Radio Communications › N/A - No Subsystem › MF Radio installation
Issued 4 May 2023
Resolved
All radiotelephones must contain the MMSI and integral GPS capabilities or must be connected to an electronic position-fixing device. The VHF radio needs to be linked to GPS.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 June 2023
Resolved 25 May 2023
Resolution: Corrected.
05 - Radio Communications › N/A - No Subsystem › Distress messages: obligations and procedures
Issued 4 May 2023
Resolved
Vessels on LC routes must be equipped with the proper amount of distress flares. The vessel has 9 of 12 flares onboard.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 18 May 2023
Resolved 25 May 2023
Resolution: Corrected.
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 4 May 2023
Resolved
All escape hatches and doors and other emergency exits used for escape must be marked with 'EMERGENCY EXIT, KEEP CLEAR' on both sides with at least 2" letters. Multiple hatches and doors didn't have it on both sides or need to be re-stenciled.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 June 2023
Resolved 25 May 2023
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 18 May 2022
Resolved
Electrical equipment on a vessel must be installed and maintained to prevent electrical ignition of flammable vapors. 110V AC outlet was found to be in unserviceable condition. Replace outlet to the satisfaction of the Marine Inspector.
46CFR183.200
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 June 2022
Resolved 2 June 2022
Resolution: Replaced in kind.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 18 May 2022
Resolved
Wet exhaust flex hose coupling on both MDE's deteriorated. Repair as original.
46CFR182.425
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 June 2022
Resolved 2 June 2022
Resolution: Hose clamps replaced on both MDE wet exhaust hoses.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 18 May 2022
Resolved
All machinery and equipment must be installed and maintained. Bilge discharge hose on port side forward bulkhead in engine room deteriorated. Repair as original.
46CFR182.100
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 June 2022
Resolved 2 June 2022
Resolution: Nonmetallic flexible hose renewed.
Engineering › Diesel Engine (propulsion-direct drive) › Exhaust Manifold
Issued 23 May 2017
Resolved
Remove/inspect exhaust discharge hose on #1 generator. Reinstall with hose clamps properly located on fitting. 46 CFR 182.720
Due 30 May 2017
Resolved 24 May 2017
Resolution: Exhaust hose was properly clamped with no apparent damage to existing flexible hose. //s// [name withheld], CWO4
Lifesaving › Lifefloat › Floating Electric Waterlight
Issued 23 May 2017
Resolved
Provide proper battery for lifefloat waterlight. Battery too heavy. 46 CFR 180.70(d)(1)
Due 30 May 2017
Resolved 24 May 2017
Resolution: Verified battery replacement with approved battery. Tested waterlight floating capability. Sat. //s// [name withheld], CWO4
Accommodation/Occupational Safety › Occupational Safety › Tripping/Falling Hazard
Issued 23 May 2017
Resolved
Secure top of engine room ladder.
Due 30 May 2017
Resolved 24 May 2017
Resolution: New brackets installed, verified sturdiness of ladder. //s// [name withheld], CWO4
Pollution Prevention/Response › Prevention Equipment › Sewage System Piping
Issued 23 May 2017
Resolved
Provide proper repair on aft sewage line in port side of stern compartment. Sewage leaking into drip bucket. 46 CFR 176.818
Due 30 May 2017
Resolved 24 May 2017
Resolution: Verified repair on sewage line. Leaking stopped. //s// [name withheld], CWO4
Electrical › Electrical Distribution System (service) › Conductor
Issued 15 April 2016
Resolved
Connect conductor wires in crew space ptsd fin and to sea valve in steering gear room
46CFR183.01-15
Action required: 705 - Other - as specified
Due 2 May 2016
Resolved 27 April 2016
Engineering › Fuel Oil Storage/Transfer System › Piping
Issued 15 April 2016
Resolved
Fuel fill piping system port & starboard at tank need conductors or grounding wires attached
46CFR182.20-30
Action required: 705 - Other - as specified
Due 2 May 2016
Resolved 27 April 2016
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 15 April 2016
Resolved
Replace ring buoy light next to bridge
46CFR180.30-1
Due 26 April 2016
Resolved 16 May 2016
Resolution: Observed properly operating ring life buoy waterlight IVO bridge.
Electrical › Electrical Distribution System (service) › Wiring
Issued 15 April 2016
Resolved
Remove or cap two dead end wires located on overhead in steering gear space
46CFR183.01-15
Action required: 705 - Other - as specified
Due 2 May 2016
Resolved 27 April 2016
Fire Fighting › Structural - A Class Divisions › Machinery Spaces
Issued 20 January 2016
Resolved
PROPERLY PLUG HOLE IN OVERHEAD OF GEN SPACE TO THE GALLEY, TO SATISFACTION OF ATTENDING MARINE INSPECTOR.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 5 February 2016
Resolved 4 February 2016
Resolution: Vessel plugged the hole in overhead.