Records from 1981 to 2007. Most recent: inspection, 9 November 2007.
Inspection history · 73
9 November 2007
ISPS II Exam · PII Safety Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3096015
16 February 2006
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2586259
10 February 2006
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2593970
10 February 2006
Type not recorded
No type recorded · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 2615421
13 December 2005
Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2559966
5 December 2005
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2545944
5 December 2005
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2545971
7 September 2004
Internal Structural Exam · Re-Inspection · Cargo Tank Internal · Examination of Repairs · Hull Examination · MTSA Verification
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2188916
17 May 2004
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 2070558
11 December 2003
Administrative Inspection
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1962813
18 November 2003
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 1950151
25 August 2003
Re-Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 1886440
3 June 2003
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1816020
28 October 2002
Administrative Inspection
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1697287
18 September 2002
Administrative Inspection · Hull Examination · COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1676888
14 August 2002
Administrative Inspection
Administrative · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1661597
8 September 2001
Type not recorded
No type recorded · Station Port Aransas · USCG Heartland District (CGD-H) · Activity 1521959
21 June 2001
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1065409
26 May 2001
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 189002
22 March 2001
Examination of Repairs · Damage Survey
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1464357
20 June 2000
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1050666
9 February 2000
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1046321
5 January 2000
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 813761
31 August 1999
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 770370
9 August 1999
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 203486
9 August 1999
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 221469
6 August 1999
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 780851
20 July 1999
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1369287
24 February 1999
Administrative
Administrative · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1130988
18 February 1999
Administrative
Administrative · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 795180
21 January 1999
Permit to Proceed
Administrative · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 789478
21 January 1999
Hull Examination
Physical examination · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 1388708
30 April 1998
Administrative
Administrative · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 1438702
1 January 1998
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1119233
7 September 1997
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 786010
19 August 1997
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1456522
18 June 1997
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 775757
18 March 1997
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1103938
20 August 1996
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1090148
20 May 1996
Damage Survey
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1455380
19 May 1996
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 50784
25 August 1995
COI Inspection · Hull Examination
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1363386
2 August 1995
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 697443
9 June 1995
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 6280
14 December 1994
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1403869
23 August 1994
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1170965
5 April 1994
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1165834
6 January 1994
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1161712
7 December 1993
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1158793
11 November 1993
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1470380
13 April 1993
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1145232
1 February 1993
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 105100
27 January 1993
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 829148
6 January 1993
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1438019
29 December 1992
Hull Examination
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1359462
6 January 1992
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 946739
11 November 1991
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1246406
2 October 1991
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1253754
19 November 1990
Re-Inspection · Hull Examination
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1212426
17 November 1989
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 914979
8 November 1989
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 899706
10 January 1989
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 896561
13 November 1987
Hull Examination · COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1311394
9 June 1987
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1324992
10 February 1987
Administrative
Administrative · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1320241
11 December 1986
Re-Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1030009
15 January 1986
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 994327
9 January 1986
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1300924
26 November 1985
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1301380
31 May 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1290573
31 January 1985
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1284323
1 December 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 971470
19 November 1981
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 963922
Engineering › Diesel Engine (auxiliary) › Overspeed Device
Issued 13 December 2005
Resolved
Demonstrate operation of the overspeed device, port genset.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 December 2005
Resolution: Tested sat.
Engineering › Steering Gear System › Rudder
Issued 13 December 2005
Resolved
Correct excessive leak through both rudder tubes.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 December 2005
Resolution: Adjusted packing.
Engineering › Diesel Engine (auxiliary) › Gear/Clutch Starter (air motor)
Issued 13 December 2005
Resolved
Demonstrate proper operation of air start system, Port generator.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 December 2005
Resolution: Demonstrated with sat results.
Engineering › Fuel Oil Service System › Filter
Issued 13 December 2005
Resolved
Remove pet-cocks from filter housings, both main diesel engines.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 December 2005
Resolution: Petcocks removed and plugs installed.
Engineering › Fuel Oil Storage/Transfer System › Piping
Issued 13 December 2005
Resolved
Correct leaks along both fuel pipes, fwd bulkhead, port side by way of engine room overhead.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 16 December 2005
Resolution: Leaks corrected.
Engineering › Fuel Oil Storage/Transfer System › Pump
Issued 13 December 2005
Resolved
Correct leaking packing gland in transfer pump.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 December 2005
Resolution: Leaks corrected.
Operations/Management › Bilge/Bilge System Management › Control of Oil Mixtures
Issued 13 December 2005
Resolved
Remove excessive fuel / oil / water from bilges.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 16 December 2005
Resolution: All slops and waste removed.
Operations/Management › Bilge/Bilge System Management › Control of Oil Mixtures
Issued 13 December 2005
Resolved
Make available space in waste oil tank to recieve additional slops.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 16 December 2005
Resolution: Pumped out all waste.
Lifesaving › Lifejacket/PFD (General) › Marking
Issued 13 December 2005
Resolved
Stencil all life jackets with vessel name.
Action required: 705 - Other - as specified
Due 13 January 2006
Resolved 14 December 2005
Resolution: Lifejackets stenciled with vsl name.
Engineering › Shafting/Propeller Arrangements › Stern Tube
Issued 13 December 2005
Resolved
Install either lock-nuts or double-nut all packing gland fasteners for propulsion shafts.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 December 2005
Resolution: Double nuts installed.
Lifesaving › Inflatable Liferafts › Hydrostatic Release Unit
Issued 25 August 2003
Resolved
Renew hydrostat release on both liferafts.
Action required: 17 - Rectify deficiencies prior to departure
Due 25 September 2003
Resolved 25 August 2003
Navigation › Piloting/Steering › Coast Guard Light List
Issued 25 August 2003
Resolved
Provide 2003 Light List.
Action required: 17 - Rectify deficiencies prior to departure
Due 25 September 2003
Resolved 25 August 2003
Navigation › Piloting/Steering › US Coast Pilot
Issued 25 August 2003
Resolved
Provide 2003 Coast Pilot.
Action required: 17 - Rectify deficiencies prior to departure
Due 25 September 2003
Resolved 25 August 2003
Electrical › Electrical Distribution System (service) › Switch
Issued 25 August 2003
Resolved
Repair port main engine shutdown in pilothouse.
Action required: 17 - Rectify deficiencies prior to departure
Due 25 September 2003
Resolved 25 August 2003
Lifesaving › Lifebuoys › Quantity
Issued 25 August 2003
Resolved
Renew retro tape on starboard main deck lifering.
Action required: 17 - Rectify deficiencies prior to departure
Due 25 September 2003
Resolved 25 August 2003
Documentation
Issued 20 July 1999
Resolved
PROVIDE UPDATED TONNAGE TO VESSEL DOCUMENTATION CENTER.
Condition: Unknown
Due 20 July 1999
Resolved 20 July 1999
Fire Fighting
Issued 19 August 1997
Resolved
Renew fire extinguisher brackets in engine room.
Condition: Unknown
Due 8 October 1997
Resolved 8 October 1997
Construction/Loadline
Issued 20 May 1996
Resolved
REPAIR STRUCTUAL DAMAGE TO PORT POTABLE WATER TANK.
Condition: Unknown
Due 20 May 1996
Resolved 20 May 1996
Engineering
Issued 11 November 1993
Resolved
PROVIDE APPROVED ENGINEERING AUTOMATED CONTROL/MONITORING TEST PROCEDURES. NOT ON BOARD AS REQUIRED.
Condition: Unknown
Due 11 November 1993
Resolved 11 November 1993
Engineering
Issued 11 November 1993
Resolved
REPAIR PORT VENTILATION EXHAUST MOTOR. INOPERABLE DUE TO EXCESSIVE BEARINGWEAR.
Condition: Unknown
Due 11 November 1993
Resolved 11 November 1993
Engineering
Issued 6 January 1993
Resolved
PROVE OPERATION OF PORT AND STBD SHAFT TACHOMETERS SHOWING DIRECTION AND SPEED AT ALL INSTALLED LOCATIONS.
Condition: Unknown
Due 6 January 1993
Resolved 6 January 1993
Deck/Cargo
Issued 11 November 1991
Resolved
PROVE PROPER OPERATION OF RELIEF VALVES FOR ALL SIX (06) P-TANKS.
Condition: Unknown
Due 11 November 1991
Resolved 11 November 1991
Engineering
Issued 11 November 1991
Resolved
PROVE PROPER OPERATION OF RELIEF VALVES FOR BOTH CONTROL AIR AIR RECEIVERS.
Condition: Unknown
Due 11 November 1991
Resolved 11 November 1991
Unknown
Issued 8 November 1989
Resolved
REPLACE WASTED RETAINING STRAPS ON AIR CLEANER FOR THE CABLE WINCH LOCATED AT THE FORWARD MOST SECTION OF THE AFT DECK TO COMPLY WITH GOOD MARINE PRACTICE.
Condition: Unknown
Due 8 November 1989
Resolved 8 November 1989
Electrical
Issued 26 November 1985
Resolved
INSTALL A NEW EMERGENCY LIGHT IN THE AFT END OF THE TUNNEL LEADING TO THE MACHINERY SPACE.
Condition: Unknown
Due 26 November 1985
Resolved 26 November 1985
Unknown
Issued 26 November 1985
Resolved
INSTALL A STANDARD DISCHARGE CONNECTION ON THE DECK DISCHARGE PIPING.
Condition: Unknown
Due 26 November 1985
Resolved 26 November 1985
Navigation
Issued 26 November 1985
Resolved
MAKE REPAIRS TO THE 25KW RADAR AND OPERATIONALLY TEST IN THE PRESENCE OF A MARINE INSPECTOR.
Condition: Unknown
Due 26 November 1985
Resolved 26 November 1985
Engineering
Issued 31 January 1985
Resolved
REPAIR THE REMOTE ENGINE SHUTDOWN TO MAKE IT OPERABLE.
Condition: Unknown
Due 31 January 1985
Resolved 31 January 1985