Records from 2007 to 2026. Most recent: inspection, 24 March 2026.
Inspection history · 18
24 March 2026
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8331021
16 March 2026
In-Service Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8326805
5 October 2025
PSC B
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 8245882
1 April 2024
PSC B
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7883824
8 October 2022
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7573820
4 August 2022
Type not recorded
No type recorded · Sector Virginia · USCG East District (CGD-E) · Activity 7529785
28 April 2022
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7439784
28 April 2022
COE-Administrative
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7440260
18 February 2021
PSC B · Administrative Inspection
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7142139
18 November 2020
Type not recorded
No type recorded · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7097499
13 December 2019
ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6873184
10 January 2017
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6068514
21 October 2015
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 5747483
12 February 2012
Ballast Water Examination · MARPOL Annex I Examination · PII Safety Exam · ISPS II Exam
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 4239364
18 October 2007
Type not recorded
No type recorded · Sector Portland · USCG Northwest District (CGD-NW) · Activity 3082822
9 October 2007
Ballast Water Examination · PII Safety Exam · ISPS II Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3075487
7 October 2007
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3074752
4 October 2007
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3073152
09 - Working and Living Conditions › 092 - Working Conditions › Machinery
Issued 16 March 2026
Resolved
The machinery shall be of a design and construction adequate for the service for whcih they are intended and shall be installed and protected as to reduce to a minimum any danger to persons on board.
74 SOLAS (04) II-1/26.1
PSCO received report of reduction of propulsion and observed failure of exhaust valve on #3 cylinder.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 March 2026
Resolution: Vessel submitted satsfactory class report.
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 1 April 2024
Resolved
Fire fighting systeams and appliances shall be ket in good working order and readily available for immediate use. PSCO observeed the emergency fire pump unable to build pressure in firemain system. 74SOLAS20 II-2/ 14.2.1.2, Restricted, Code 60
Action required: 60 - Rectify deficiencies prior to movement
Due 1 April 2024
Resolved 2 April 2024
Resolution: Received, reviewed and accepted class report from KR. The priming water line was found to be clogged and cleaned by the Chief Engineer, and the emergency fire pump was confirmed to be in good working order by the attending surveyor.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 1 April 2024
Resolved
In multi engine installations which are supplied from the same fuel source, means of isolating the fuel supply and spill piping to individual engines shall be provided. PSCO observed the quick closing emergency fuel supply shut off valves for auxiliary engines #1 and #2 were unable to close via remote actuating station. Demonstrate operational readiness of all fuel shut off valves.
Action required: 60 - Rectify deficiencies prior to movement
Due 1 April 2024
Resolved 2 April 2024
Resolution: Received, reviewed and accepted class report from KR. The grand packings were replaced and the quick-closing valve for all G/E's was confirmed to be in good working order by the attending surveyor.
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 12 February 2012
Resolved
1730-Oil filtering equipment shall be provided with alarm arrangements and automatically stop when the effluent exceeds 15 ppm. During routine maintenance of the OWS on 26 Jan 2012, it was unable to reach zero with the introduction of fresh water. Unable to OCM at this time. Prior to departure, conduct satisfactory test of system with USCG Inspector in attendance. MARPOL I/14.7 17(a)(c)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 13 February 2012
Operations/Management › Drills/Instruction › Fire
Issued 9 October 2007
Resolved
Unsatisfactory Fire Drill due to doors to galley space left open, and crew casualty being ignored by crew. Cite: 74/78 SOLAS as ammended CH III Reg 19.3.4
Action required: 705 - Other - as specified
Due 9 October 2007
Resolved 9 October 2007
Resolution: Conducted 2nd fire drill.