Records from 2009 to 2025. Most recent: inspection, 19 September 2025.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,619 / net 1,619
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderJEFFBOAT LLC · JEFFERSONVILLE, IN, UNITED STATES · built 2009
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portHOUSTON, TX
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 7 February 2026 · expires 31 March 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1619 - Simplified, Gross Ton
1619 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 25
19 September 2025
Type not recorded
No type recorded · Marine Safety Detachment St. Paul · USCG Heartland District (CGD-H) · Activity 8237498
27 August 2024
COI Inspection · Internal Structural Exam · MTSA Verification · Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7971774
4 February 2023
Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7632196
9 November 2021
Type not recorded
No type recorded · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 7354189
16 August 2021
MTSA Verification · Periodic Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7281984
11 September 2020
Bulk Liquid Transfer Monitor
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7055925
22 July 2019
MTSA Verification · Cargo Tank Internal · Internal Structural Exam · Deficiency Check · Drydock Exam · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6758214
9 October 2018
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6552718
5 October 2017
MTSA Verification · Annual Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6281505
30 December 2016
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6063844
31 August 2016
Periodic Inspection · MTSA Verification · Examination of Repairs · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5988720
19 October 2015
MTSA Verification · Administrative Inspection · Examination of Repairs · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5746081
7 April 2015
Damage Survey
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5102193
21 July 2014
MTSA Verification · COI Inspection · Internal Structural Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4923053
19 September 2013
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4716027
4 October 2012
Examination of Repairs · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4455161
26 September 2012
Periodic Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 4450894
13 March 2012
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4262554
12 October 2011
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4166490
30 January 2011
Type not recorded
No type recorded · Marine Safety Detachment Peoria · USCG Heartland District (CGD-H) · Activity 3935845
7 October 2010
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3865252
20 June 2010
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3776113
30 April 2010
Damage Survey
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3727599
29 May 2009
Administrative Inspection
Administrative · Commandant (CG-CVC) · Activity 3489543
3 April 2009
Internal Structural Exam · Initial Construction-Excluding Oversight · Hull Examination · MTSA Verification · Initial Certification · Drydock Exam
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 3520068
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 16 August 2021
Resolved
Vapor collection piping must be fixed piping.
Vapor collection piping valve was removed from system leading to vapor connection points and blank flanged.
Install isolation valve and conduct vapor tightness test. Provide documentation to attending marine inspector prior to cargo operations.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 17 August 2021
Resolution: Vessel rep provided documentation that the deficiency was corrected. Cleared 835.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 26 July 2019
Resolved
The vessel owner will ensure that the tank vessel is of a structure suitable for the carriage of flammable and/or combustible liquids in bulk and for the proper grade or grades of cargo the vessel carries while in service. Marine Inspector observed cargo leak from #2P cargo tank in void #4P, Bay #6 during ISE. Repairs to be made to original design and a satisfactory pressure/leak test witnessed by attending USCG Marine Inspector prior to issuance of COI. 46CFR31.10-15(a)
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Resolved 22 August 2019
Resolution: Verified repairs - all sat
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 22 July 2019
Resolved
The vessel owner will ensure that the tank vessel is of a structure suitable for the carriage of flammable and /or combustible liquids in bulk and for the proper grade or grades of cargo the vessel carries while in service. Marine Inspector observed unsatisfactory repair of #3P AFT and #4P FWD Bulkhead (unsatisfactory welds due to excessive undercutting and porosity). In addition, two repairs in rake bow, port side with insufficient relief cuts (less than 2"). Welds to be back gouges and rewelded to the satisfactory of attending [name withheld], the repair to the bulkhead shall be pressure/leak tested to the satisfactory of attending MI prior to issuance of COI. 46CFR31.10-15(a)
Action required: 705 - Other - as specified
Resolved 22 August 2019
Resolution: verified repairs - all sat
Electrical › Electric Generation Source (service) › Generator Cable
Issued 31 August 2016
Resolved
Coast Guard Sector Houston personnel, while conducting a periodic inspection, noted the barge's cargo pump prime mover is not located in compliance with Class 1, Division 1 requirements.
Action required: 705 - Other - as specified
Due 1 January 2017
Resolved 5 October 2017
Resolution: New COI & CAA authorize only grade E cargos.
Deck/Cargo › Holds/Tanks › Independent Tank
Issued 26 September 2012
Resolved
Make permanent repairs to the cargo tank leak in the #5 port side wing void, upper aft inboard corner.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 4 October 2012
Resolution: Witnessed satisfactory air/soap test of cargo tank, from #4 port side wing void. (correct void no.)
Documentation › Safety/Response Plans/Programs › Vessel Response Plan
Issued 24 April 2009
Resolved
The vessel series must be verified by the plan holder and amend the TVRP accordingly.
Due 24 May 2009
Resolved 14 July 2009
Resolution: Verified VRP letter from MSC.