Inspection history · 90
21 March 2025
Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8097577
1 February 2024
Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7846807
26 January 2023
Deficiency Check · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7627696
23 February 2022
COI Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7400734
18 August 2020
Examination of Repairs · Cargo Tank Internal · Administrative Inspection · COI Inspection · Internal Structural Exam · MTSA Verification · Drydock Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7036125
10 February 2020
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6937256
27 January 2020
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6897746
18 May 2019
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6689960
30 October 2018
Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6571483
16 October 2018
Administrative Inspection · Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6562549
9 August 2018
Examination of Repairs
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6507029
8 August 2018
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6506330
18 June 2018
Examination of Repairs · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6447868
14 June 2018
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6444289
14 June 2018
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6444356
22 November 2017
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6311614
8 November 2016
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6037583
25 September 2015
Examination of Repairs · MTSA Verification · COI Inspection · In-Service Inspection · Drydock Exam · Internal Structural Exam · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5728589
17 November 2014
Damage Survey · Deficiency Check · Cargo Tank Internal
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5025395
15 November 2014
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 5027144
15 November 2014
Type not recorded
No type recorded · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 5027290
23 July 2014
Periodic Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4931454
2 December 2013
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4762816
8 October 2013
Administrative Inspection · Internal Structural Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4743508
25 September 2012
Cargo Tank Internal
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4451510
10 May 2012
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4307806
5 July 2011
COI Inspection · MTSA Verification
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 4069831
16 September 2010
Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3851354
8 July 2010
Annual Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3791595
21 May 2010
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3743731
13 August 2009
Deficiency Check
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3564034
10 August 2009
COI Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3561387
15 December 2008
Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3379987
10 July 2008
Annual Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3253529
10 January 2008
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3128011
28 August 2007
Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3040763
11 July 2006
COI Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 2709545
20 March 2006
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2605578
21 December 2005
Annual Inspection · MTSA Verification
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 2554536
14 October 2005
Hull Examination · Internal Structural Exam · Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2514323
29 September 2004
Periodic Inspection · MTSA Verification
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 2208592
30 January 2004
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 1998702
7 July 2003
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1838572
10 October 2002
Cargo Tank Internal · Internal Structural Exam
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1687970
23 August 2002
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1664463
1 October 2001
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1073665
6 July 2001
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1393715
21 September 2000
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1430917
18 September 2000
Deficiency Check · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 822565
31 July 2000
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 821061
13 August 1999
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1434914
23 April 1999
Type not recorded
No type recorded · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 92268
4 August 1998
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1454591
8 October 1997
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 777331
8 October 1997
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1378184
19 August 1997
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1456504
4 September 1996
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1467483
10 January 1996
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 678824
5 January 1996
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 199708
5 January 1996
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 199710
5 January 1996
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 766103
22 August 1995
Hull Examination · COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1434298
5 February 1995
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 41811
13 December 1994
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 135878
22 September 1994
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 871591
15 September 1994
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1178399
11 August 1994
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1382814
13 September 1993
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 149924
23 August 1993
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 826991
23 October 1992
Hull Examination · Examination of Repairs
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 958262
16 September 1992
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1245878
20 August 1992
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1243948
9 September 1991
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 942423
16 November 1990
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 932808
12 September 1990
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 899966
24 August 1990
COI Inspection · Deficiency Check · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 908647
5 November 1989
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 441801
24 October 1989
Examination of Repairs
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 922102
27 September 1989
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1226197
6 October 1988
Hull Examination · COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1203576
22 September 1987
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1319180
12 March 1987
Hull Examination
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1323934
18 September 1986
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1311938
12 September 1985
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 993231
3 January 1985
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 976233
24 October 1984
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1282737
20 September 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 974685
22 November 1983
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1279592
22 September 1982
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1271250
30 October 1981
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1276141
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 21 March 2025
Resolved
Systems and equipment. Except as noted in paragraph (c) of this section, this part applies to automation of vital systems or equipment that—(1) Is automatically controlled or monitored;(2) Is remotely controlled or monitored; or(3) Utilizes automation for the purpose of replacing specific personnel or to reduce overall crew requirements.
Vessel is required to provide manufacturer's instruction
on how they will test and ensure vital systems of thermal fluid heater prior to carriage of cargo. Vessel will follow manufacturer's instruction, conduct all applicable testing, and submit satisfactory test reports to USCG.
Action required: 701 - Prior to carriage of passengers/cargo
Due 1 September 2025
Resolved 6 May 2025
Resolution: CG attendance verified rectification.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 21 March 2025
Resolved
All portable and semiportable extinguishers on board tank vessels shall be of an approved type.
Both portable fire extinguishers required to be on board were past their designed service date. Vessel is require
replace portable extinguishers prior to carriage of
cargo.
Action required: 701 - Prior to carriage of passengers/cargo
Due 21 March 2025
Resolved 6 May 2025
Resolution: CG attendance verified rectification.
14 - Pollution Prevention › 141 - MARPOL Annex I › Oil fuel tank protection
Issued 21 March 2025
Resolved
A ship of 100 gross tons or more constructed before July 1, 1974, and a ship of 100 or more but less than 300 gross tons constructed after June 30, 1974 must meet paragraph (a)(1) of this section.
Paragraph (a)(1) states that the required capacity under a fuel oil tank will be one-half barrel. MI identified non fixed and worn containment that does not meet the requirements of containing one-half barrel. Company is to install fixed containment at their next dry dock prior to USCG COI renewal.
Action required: 705 - Other - as specified
Due 21 March 2025
Resolved 6 May 2025
Resolution: CG attendance verified rectification.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 21 March 2025
Resolved
Nonmetallic flexible hose may be used in lube oil, fuel oil and fluid power systems only where flexibility is required and in lengths not exceeding 30 inches.
MI identified two flexible hoses on the main generator exceeding 30 inches. Company has been instructed to rectify at next drydock prior to USCG COI renewal.
Action required: 705 - Other - as specified
Due 21 March 2025
Resolved 6 May 2025
Resolution: CG attendance verified rectification.
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 26 January 2023
Resolved
Vent outlets from all tanks which may emit flammable or combustible vapors, such as bilge slop tanks and contaminated drain tanks, must be fitted with a single screen of corrosion-resistant wire of at least 30 by 30 mesh, or two screens of at least 20 by 20 mesh spaced not less than one-half inch (13mm) nor more than 1 1/2 inches (38mm) apart. The clear area through the mesh must not be less than the internal unobstructed area of the required pipe.
Marine inspector observed a 3/8 inch hole on the gooseneck vent for the onboard diesel fuel tank approxomately 2 inches higher than the installed flame screen.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 31 January 2023
Resolution: Corrected gooseneck vent flame screen to satisfaction of [name withheld] 46 CFR 56.50-85.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other cargo/timber/deck/construction
Issued 30 October 2018
Resolved
Cargo tanks shall be supported on foundations of steel or other suitable material. The saddle supports were cracked on frame 12 in the port side aft tank, frame 11 and 12 of the STBD side aft tank, and frame 4 in the Port side FWD tank. The listed supports must be repaired to the satisfaction of the attending MI.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 9 November 2018
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 30 October 2018
Resolved
Each generator prime mover must have an over speed device that is independent of the normal operating governor and adjusted so that the speed cannot exceed the maximum rated speed by more than 15 percent. The crew was unable to prove proper operation of the over speed trip. Repairs or training must be conducted in order to exhibit proper operation of the over speed trip at 115% of the generator rating to the satisfaction of the attending inspector.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 8 November 2018
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 30 October 2018
Resolved
Each ungrounded system must be provided with a suitably sensitive ground detection system which provides continuous indication of circuit status to ground. During inspection it was noted that only two of the three lights on ground detection system were lit. Verify whether there is a ground or if the indicator bulb needs to be changed. Exhibit proper operation to the satisfaction of the attending inspector.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 8 November 2018
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other cargo/timber/deck/construction
Issued 30 October 2018
Resolved
Gravity type cargo tanks shall be constructed and tested as required by standards established by the American Bureau of Shipping or other recognized classification society. Product was found seeping from under the tank lagging. Lagging must be removed in order to verify the integrity of the cargo tank.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 8 November 2018
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 8 August 2018
Resolved
Crossover valve malfunction.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Due 11 August 2018
Resolved 9 August 2018
Resolution: Valve had been inserted incorrectly. Valve was inserted correctly.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 17 November 2014
Resolved
Vessel needs to conduct a Cargo Tank Internal Exam for both port and starboard cargo tank prior to loading cargo.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 19 December 2014
Resolution: Conducted satisfactory cargo tank internal exam of both cargo tanks. Inspected repairs to baffle in port cargo tank - all satisfactory.
Electrical › Electrical Distribution System (service) › Switch
Issued 10 August 2009
Resolved
High temp reset switch for electric heater doesn't work.
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 August 2009
Resolved 14 August 2009
Resolution: Reset switch repaired and function tested sat.
Stability › Watertight Integrity › Weathertight Enclosure
Issued 10 August 2009
Resolved
port bow void hatch- knife edge is wasted away and much be cropped out and renewed.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 August 2009
Resolved 14 August 2009
Resolution: Port bow void hatch repaired.
Stability › Watertight Integrity › Weathertight Enclosure
Issued 10 August 2009
Resolved
several hatches to wing voids had severe rust to the point it was pushing out the gaskets and some gaskets covered in paint not making the hatch watertight.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 August 2009
Resolved 14 August 2009
Resolution: All hatch gaskets replaced.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 28 August 2007
Resolved
Replace machinery guard on main generator.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 12 September 2007
Resolved 5 September 2007
Resolution: Send email with pictures of new machinery guard.
Construction/Loadline
Issued 8 October 1997
Resolved
REPAIR DAMAGE PLATEING OF THE GUNNEL/RAPPER SECTION IN THE NO. 3&4 PORT WING VOIDS.
Condition: Unknown
Due 8 October 1997
Resolved 8 October 1997
Construction/Loadline
Issued 8 October 1997
Resolved
MAKE PERMENT REPAIRS TO THE DAMAGED GUNNEL/RAPPER PLATING IN NO. 3&4 PORT VOIDS.
Condition: Unknown
Due 8 October 1997
Resolved 8 October 1997
Deck/Cargo
Issued 19 August 1997
Resolved
REMOVE/RE-FURBISH CARGO HANDLING WINCH.
Condition: Unknown
Due 22 August 1997
Resolved 25 August 1997
Construction/Loadline
Issued 19 August 1997
Resolved
REPLACE ALL DEFICIENT GASKETS ON MAN-WAY COVERS.
Condition: Unknown
Due 22 August 1997
Resolved 25 August 1997
Navigation
Issued 19 August 1997
Resolved
RE-PAINT DRAFT MARKS AND VESSEL NAME IN ALL APPLICABLE LOCATIONS.
Condition: Unknown
Due 22 August 1997
Resolved 25 August 1997
Deck/Cargo
Issued 19 August 1997
Resolved
PROVIDE HYDRO TEST DATE, OTHERWISE REMOVE CARGO HOSE.
Condition: Unknown
Due 22 August 1997
Resolved 25 August 1997
Deck/Cargo
Issued 20 August 1992
Resolved
PROVE PROPER OPERATION OF EMERGENCY SHUT DOWNS FOR CARGO PUMPS. (PUMPS WEREFROZEN WITH SULFUR)
Condition: Unknown
Due 15 October 1992
Resolved 22 September 1992
Deck/Cargo
Issued 20 August 1992
Resolved
PROVE PROPER OPERATION OF HIGH TEMP. SWITCH FOR #2 FUSE BLOCK IN THERMAL FLUID HEATER PRIOR TO USE IN A CARGO TRANSFER.
Condition: Unknown
Due 15 October 1992
Resolved 22 September 1992
Deck/Cargo
Issued 24 August 1990
Resolved
PRIOR TO TRANSFER OF CARGO, PROVIDE SUITABLE DOCUMENTATION OF TESTING OF CARGO HOSES.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 24 August 1990
Resolved
PRIOR TO ANY TRANSFER OF CARGO, CONDUCT OPERATIONAL TEST OF THE THERMAL FLUID HEATER IN THE PRESENCE OF A COAST GUARD MARINE INSPECTOR.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 24 August 1990
Resolved
PROVIDE COPY OF APPROVED OPERATIONS MANUAL FOR THE THERMAL FLUID HEATER.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Electrical
Issued 24 August 1990
Resolved
PRIOR TO ANY CARGO TRANSFER, CONDUCT OPERATIONAL TEST OF THE GENERATOR/ SWITCHBOARD IN THE PRESENCE OF A COAST GUARD MARINE INSPECTOR.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 24 August 1990
Resolved
PRIOR TO ANY CARGO TRANSFER, DEMONSTRATE PROPER OPERATION OF ALL EMERGENCY SHUT DOWNS IN THE PRESENCE OF A COAST GUARD MARINE INSPECTOR.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 24 August 1990
Resolved
PRIOR TO ANY CARGO TRANSFER, INSTALL GASKETS ON ALL CARGO TANK HATCHES.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 24 August 1990
Resolved
PRIOR TO ANY CARGO TRANSFER, PROVIDE SUITABLE DOCUMENTATION OF TESTING OF CARGO AND HEATER PIPING.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 24 August 1990
Resolved
PROVIDE, AND MAINTAIN ON BOARD A COPY OF CARGO TRANSFER PROCEDURES.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Accommodation/Occupational Safety
Issued 24 August 1990
Resolved
REMOVE TRASH/OIL FROM DECK AND IN HEATER CONTROL ROOM.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Accommodation/Occupational Safety
Issued 24 August 1990
Resolved
REPAINT RED PENNANT.
Condition: Unknown
Due 24 August 1990
Resolved 24 August 1990
Deck/Cargo
Issued 20 September 1984
Resolved
REPLACE EMERGENCY SHUTDOWN CABLE ON PORT PUMP ENGINE.
Condition: Unknown
Due 20 September 1984
Resolved 20 September 1984
Engineering
Issued 20 September 1984
Resolved
REPAIR/REPLACE INSULATION AS NECESSARY ON ALL EXPOSED THERMAL FLUID LINES.
Condition: Unknown
Due 20 September 1984
Resolved 20 September 1984
Deck/Cargo
Issued 20 September 1984
Resolved
REPLACE PORT ENGINE ACCUMULATOR PRESSURE GAUGE.
Condition: Unknown
Due 20 September 1984
Resolved 20 September 1984
Engineering
Issued 20 September 1984
Resolved
OBTAIN COMMANDANT (G-MTH) APPROVAL FOR THERMAL FLUID OF DRAIN THERMAL FLUIDSYSTEM AND REFILL WITH AN APPROVED THERMAL FLUID FOR USE WITH LIQUID SULFUR; AS PER 46CFR151.50-55.
Condition: Unknown
Due 20 September 1984
Resolved 20 September 1984