Inspection history · 23
29 May 2026
Annual Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 8382933
17 April 2025
Deficiency Check · Administrative Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 8113164
20 March 2025
Internal Structural Exam · Administrative Inspection · COI Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 8093255
23 April 2024
MTSA Verification · Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7900218
9 June 2023
Administrative Inspection · Periodic Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7703961
22 July 2022
Type not recorded
No type recorded · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7554508
19 April 2022
Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7401867
11 March 2021
Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7146878
10 February 2020
Examination of Repairs · Cargo Tank Internal · Administrative Inspection · Drydock Exam · MTSA Verification · Internal Structural Exam · COI Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6906309
20 September 2019
MTSA Verification · Annual Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6815811
20 August 2018
Annual Inspection · MTSA Verification · Administrative Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6517538
22 August 2017
Deficiency Check · MTSA Verification · Administrative Inspection · Plan Review (Other than "T") · Periodic Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6243708
7 March 2017
Type not recorded
No type recorded · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6101440
22 June 2016
Annual Inspection · MTSA Verification · Administrative Inspection · Deficiency Check
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 5913368
28 May 2015
MTSA Verification · COI Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 5137868
27 February 2015
Internal Structural Exam · Administrative Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 5076047
9 June 2014
MTSA Verification · Administrative Inspection · Periodic Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4883996
4 June 2013
MTSA Verification · Administrative Inspection · Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4610739
22 June 2012
Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4320571
27 October 2011
Type not recorded
No type recorded · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4177246
30 September 2011
Type not recorded
No type recorded · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4158259
29 August 2011
Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4127838
16 June 2010
Initial Construction-Excluding Oversight · Administrative Inspection · Initial Certification · Hull Examination · MTSA Verification · Welding Related Inspections Qualification Testing · Deficiency Check · Cargo Tank Internal · Internal Structural Exam
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3768009
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 29 May 2026
Resolved
Shutoff valves must be installed in the fuel supply lines, one as close to each tank as practicable, and one as close to each fuel pump as practicable. Valves must be accessible at all times. Shutoff valve missing/not installed on fuel supply line at fuel pump on GENSET.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 June 2026
Resolved 3 June 2026
Resolution: Valve installed on system at GENSET.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 20 March 2025
Resolved
Each tank vessel with a cargo capacity of 1,000 or more cubic meters (approximately 6,290 barrels), loading oil or oil residue as cargo, must have one overfill device that is permanently installed on each cargo tank and meets the requirements of this section. One-meter sticks on COT 1S and 1P were found wasted. Vessel may not load cargo into these tanks until rectified.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 21 March 2025
Resolution: Received pictures of the new meter sticks installed on 1P and 1S.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 20 March 2025
Resolved
The respective piping systems installed on ships and barges must have the necessary pumps, valves, regulation valves, safety valves, relief valves, flanges, fittings, pressure gages, liquid level indicators, thermometers, etc., for safe and efficient operation of the vessel. Inoperable remote valve indicating device (open/closed) for below deck cargo piping valve located in the aft portion of the #2 starboard cargo tank. The valve could be fully opened with the device indicating the valve was closed.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 19 April 2025
Resolved 21 March 2025
Resolution: Received pictures of the corrected cargo line valve.
02 - Structural Conditions › N/A - No Subsystem › Beams, frames, floors-op. damage
Issued 20 March 2025
Resolved
All tank vessels, the construction or conversion of which is started on or after July 1, 1951, shall conform to the requirements in this subpart in construction of hulls. The following items were noted during the internal structure exam:
1. Numerous broken welds in each void space found on the outboard side cords where they attach to side shell longitudinals.
2. A gusset was found to be severely crushed in void 2 starboard.
3. Top side shell longitudinal in #1 starboard, near the aft hatch was found to be severely crushed in.
Action required: 705 - Other - as specified
Due 19 April 2025
Resolved 31 July 2025
Resolution: The deficiency was cleared to the satisfaction of an attending USCG Marine Inspector.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 20 September 2019
Resolved
Barge equipped with 1-meter gauge sticks (Over fill protection device) on barge's 4 integrated cargo tanks. 3 of 4 devices were inoperable due to deformed sticks. Properly repair 3 devices.
Action required: 10 - Deficiency Rectified
Due 20 September 2019
Resolved 20 September 2019
Resolution: Barge representative replaced all deformed stick and demonstrated proper operation by the end of the inspection.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 20 September 2019
Resolved
Oil transfer procedures (OTPs) required PIC to "set 1-meter gauge sticks for use" prior to loading. Add a line of instruction to OTPs that will require the PIC to ensure the 1 meter gauge sticks (over fill protection device) is fully functional prior to loading in protected tanks. OTP amendment notice given as per 33 CFR 155.760(b).
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 October 2019
Resolved 23 September 2019
Resolution: OTPs amended by vessel operator with appropriate instruction concerning use of overfill protection devices.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 8 September 2017
Resolved
Unapproved modification added 1 1/2 inch pipeline to cargo transfer system. Remove unapproved modification and make permanent repairs as per OCMI approved repair proposal. Further use of unapproved piping to conduct cargo transfers prohibited.
Action required: 705 - Other - as specified
Due 22 September 2017
Resolved 15 September 2017
Resolution: Proper repairs made to cargo transfer piping as per OCMI approved repair proposal.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 29 August 2017
Resolved
Un-approved piping modification/alteration installed on vessel; 1 1/2 inch cargo piping threaded and sealed with pipe putty into 6 inch cargo piping at turn of piping located adjacent to discharge side of vessel's cargo pump. Repair proposal required to properly address un-approved installation.
Action required: 705 - Other - as specified
Due 5 September 2017
Resolved 31 August 2017
Resolution: A proper repair proposal was submitted as required by vessel representative, [name withheld].
Pollution Prevention/Response › Prevention Equipment › Overfill Devices
Issued 22 August 2017
Resolved
The #1 port cargo tank overfill device, designed to meet 46 CFR 39.2003(b), was inoperable. Meter stick was warped and failed to travel as designed.
Action required: 705 - Other - as specified
Due 22 August 2017
Resolved 22 August 2017
Resolution: A new meter stick was installed and proper operation demonstrated by crew.
Construction/Loadline › Markings › Draft Marks/Indicating System
Issued 22 June 2016
Resolved
Draft marks worn and not of a contrasting color to hull.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 29 June 2016
Resolved 23 June 2016
Resolution: Draft marks were re-painted.
Engineering › Fuel Oil Service System › Valve
Issued 22 June 2016
Resolved
Diesel fuel oil system did not have a valve located at the fuel pump as required by 46 CFR 56.50-75.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 22 July 2016
Resolved 23 June 2016
Resolution: New valve installed.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Transfer Hose
Issued 17 June 2015
Resolved
Slop oil suction/discharge hose had permanent kinks and was worn though exterior rubber jacket in areas.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 17 June 2015
Resolved 17 June 2015
Resolution: This hose was replaced with brand new one while inspectors were on scene.
Pollution Prevention/Response › Prevention Equipment › Overfill Devices
Issued 17 June 2015
Resolved
Meter stick on #2 starboard tank was inoperable due to damage caused to the stick.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 17 June 2015
Resolved 17 June 2015
Resolution: This meter stick was replaced with a new one while inspectors were on scene,
Electrical › Electrical Distribution System (service) › Metallic Enclosure/Frame
Issued 17 June 2015
Resolved
Sometime after construction, vessel was outfitted with heating element/wiring/indicators located within hazardous locations and do not appear to meet Class I/Div I requirements.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 17 July 2015
Resolved 22 June 2015
Resolution: Received email, along with photos from the operator showing that all post construction heating elements, wiring, and indicators have been removed from hazardous locations.
Deck/Cargo › Cargo Stowage › General
Issued 4 June 2013
Resolved
Several cargo hatch dogs were frozen. These were corrected on the spot.
Due 21 June 2013
Resolved 21 June 2013
Resolution: Corrected on the spot
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Transfer Hose
Issued 4 June 2013
Resolved
Waste Oil Suction Hose that was listed on the testing documentation was in need of replacement. The hose was kinked. This was corrected on the spot.
Due 28 June 2013
Resolved 21 June 2013
Resolution: Corrected on the spot
Construction/Loadline › Markings › Draft Marks/Indicating System
Issued 4 June 2013
Resolved
Draft Marks need to be painted. Corrected on the spot.
Due 21 June 2013
Resolved 21 June 2013
Resolution: Corrected on the spot.
Electrical › Electric Generation Source (service) › Metallic Enclosure/Frame
Issued 23 June 2010
Resolved
Repair broken intrinsically safe fitting on #1 potable water pump controller.
Condition: Improper Installation
Action required: 705 - Other - as specified
Resolved 24 June 2010
Electrical › Lighting (service) › Lighting Fixture
Issued 16 June 2010
Resolved
Repair/replace indicator light on cargo pump controller.
Action required: 705 - Other - as specified
Resolved 24 June 2010