Registered dimensions (L × B × D)56.0 ft × 22.0 ft × 9.0 ft
Registered tonnagegross 74 / net 59
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderHOUMA SHIPBLDG CO INC · HOUMA, LA, UNITED STATES · built 1970
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeShip
Hull configurationMonohull
Hailing portST LOUIS, MO
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 31 January 2026 · expires 28 February 2027
Service, as the file records itTowing Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it74 - Simplified, Gross Ton
59 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 28
20 January 2026
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8298962
9 May 2025
Administrative Inspection · COI Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8131924
8 November 2022
Drydock Exam · Internal Structural Exam · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7591416
24 February 2021
Administrative Inspection · COI Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7145556
12 January 2021
In-Service Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7123547
20 September 2019
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6816471
13 August 2019
Initial Certification · Administrative Inspection · Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6785092
7 August 2014
Industry Initiated Exam · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4947196
16 November 2013
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4766324
2 October 2013
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4728546
14 February 2013
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4599141
24 March 2012
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4328267
24 February 2012
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4251886
22 September 2011
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4159626
26 November 2010
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3903339
23 June 2010
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3809504
10 June 2010
MTSA Verification · Industry Initiated Exam
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3763083
21 May 2010
Damage Survey
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3748957
21 May 2010
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3985101
5 September 2006
Uninspected Other · MTSA Verification
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2769805
22 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1978194
12 August 1999
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 717167
5 March 1999
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 27038
8 July 1998
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 64714
30 January 1998
Uninspected Towing Vessel
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1121134
12 August 1993
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 118851
20 July 1992
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 98607
9 February 1988
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 321339
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 12 January 2021
Resolved
There must be an installed or portable bilge pump for emergency dewatering (46 CFR 143.275). Vessel's installed bilge pump could not dewater the vessel without significant time and effort to prime the pump. Demonstrate the vessel's installed bilge pump can properly dewater the vessel in case of an emergency situation to the satisfaction of the attending USCG Marine Inspector.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 February 2021
Resolved 22 March 2021
Resolution: Received TPO reports for installation of new bilge and statement of fact for Replacement in kind.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Gauges, thermometers, etc
Issued 24 September 2019
Resolved
The subject vessel does not have an approved method to monitor auxiliary generator engine RPM in the machinery space. Auxiliary generator engine RPM is required gauge for vessels regulated under Subchapter M. The installation of the required gauge shall be verified by a Coast Guard Marine Inspector or the company's approved Third Party Organization.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 24 October 2019
Resolved 3 December 2019
Resolution: Shaft tachometers installed on generator.
09 - Working and Living Conditions › 092 - Working Conditions › Protection machines/parts
Issued 16 August 2019
Resolved
Vessel equipment must be used in a manner that minimizes risk of injury or death. The pilothouse hydraulic lift system does not provide sufficient protection to prevent personnel from being injured while lowering. Procedures or equipment must be put in place to prevent personnel from being injured, to the satisfaction of the OCMI.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 16 August 2019
Resolution: Safety chains were put into place to minimize the risk of injury. The company stated they are not satisfied with these chains and plan to have other procedures put into place and possibly remove the safety chains.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Safety and environment policy
Issued 16 August 2019
Resolved
46CFR140.500: A Health and Safety Plan must be implemented on board the subject vessel. No Health and Safety Plan was found on board the vessel.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 30 August 2019
Resolved 20 November 2019
Resolution: Training conducted by company personnel to implement Health and Safety Plan.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 13 August 2019
Resolved
At least two lifebuoys on must be fitted with a floating electric water light. Only one lifebuoy was fitted with a floating electric water light.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 16 August 2019
Resolution: A working floating light has been attached the lifebuoy that previously did not have one.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 13 August 2019
Resolved
When more than one lifebuoy is carrier, at least one must not have a lifeline attached. All three lifebuoys on board had lifelines attached.
Action required: 10 - Deficiency Rectified
Due 16 August 2019
Resolved 16 August 2019
Resolution: A lifeline was removed from the life bouy as required by regulations.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 13 August 2019
Resolved
New equipment was installed on the vessel, at an unknown time. The vessel was brought back into service in 2019. Documentation must be provided demonstrating that the equipment was installed prior to Jul 20, 2018, or the newly installed equipment must meet the requirements of 46 CFR 143 Subpart C.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 30 August 2019
Resolved 20 November 2019
Resolution: Company representative provided documentation demonstrating the conversion was initiated prior to July 20, 2017, the applicability date of Subchapter M conversions.