Inspection history · 60
17 July 2026
Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8438207
19 May 2026
Drydock Exam · Administrative Inspection
Physical examination · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 8381236
8 July 2025
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8147651
6 August 2024
Periodic Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7953454
20 May 2024
Internal Structural Exam · Deficiency Check
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7917076
31 July 2023
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7726876
25 July 2022
Annual Inspection · MTSA/ISPS Verification · Administrative Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7499019
16 August 2021
Administrative Inspection
Administrative · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7288879
23 April 2021
Internal Structural Exam · COI Inspection · Drydock Exam
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7191842
28 September 2020
Annual Inspection · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7068235
14 January 2020
Administrative Inspection
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6889298
18 December 2019
Examination of Repairs · Administrative Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6876708
21 May 2019
Periodic Inspection · Internal Structural Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6686522
17 February 2019
Bulk Liquid Transfer Monitor
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 6637169
9 January 2019
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 6618427
14 September 2018
Administrative Inspection · Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6537407
14 September 2017
Annual Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6266645
6 December 2016
Deficiency Check
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6054499
5 October 2016
Administrative Inspection
Administrative · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 6017456
7 June 2016
COI Inspection · Internal Structural Exam · MTSA Verification · Drydock Exam · Deficiency Check
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 5896688
9 December 2015
Periodic Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 5778281
5 November 2015
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5760203
22 September 2015
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5726949
3 March 2015
Deficiency Check
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 5083390
15 January 2015
Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5052201
2 December 2014
Type not recorded
No type recorded · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 5036157
3 November 2014
Annual Inspection · Internal Structural Exam
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 5017802
28 September 2014
Type not recorded
No type recorded · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 4996223
13 January 2014
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 4779159
17 December 2013
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 4770402
16 December 2013
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 4770787
16 December 2013
Damage Survey
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 4771169
14 September 2013
Type not recorded
No type recorded · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 4715148
5 November 2012
Deficiency Check · Administrative Inspection · Construction Oversight
Physical examination · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 4280226
27 December 2011
Deficiency Check
Physical examination · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 4214481
20 December 2011
Administrative Inspection
Administrative · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 4211669
9 December 2011
Deficiency Check
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 4205267
2 December 2011
Hull Examination · Internal Structural Exam · COI Inspection
Physical examination · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 4197535
10 December 2010
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3912092
15 November 2010
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3891888
1 November 2010
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3889096
4 August 2010
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3814822
28 May 2010
Deficiency Check
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3761887
8 April 2010
Deficiency Check · In-Service Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3714895
8 April 2010
Deficiency Check · Administrative Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3715330
2 April 2010
Administrative Inspection
Administrative · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3708222
19 March 2010
In-Service Inspection
Physical examination · Sector Portland · USCG Northwest District (CGD-NW) · Activity 3701416
25 February 2010
Deficiency Check
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3686268
19 March 2009
Damage Survey
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3436782
19 March 2009
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3440208
3 January 2009
Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3389042
16 December 2008
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 3380974
25 September 2008
Deficiency Check
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3332316
12 June 2008
Deadweight Survey · Construction Oversight
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 3253901
31 March 2008
Type not recorded
No type recorded · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 3183813
4 February 2008
Plan Review (Other than "T")
Administrative · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3141731
18 January 2008
Annual Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 3131322
8 December 2006
Administrative Inspection
Administrative · Marine Safety Unit Sturgeon Bay · USCG Great Lakes District (CGD-GL) · Activity 2838019
28 November 2006
Hull Examination · Construction Oversight · Cargo Tank Internal · COI Inspection · In-Service Inspection · Ballast Water Examination · Initial Certification · MTSA/ISPS Verification
Physical examination · Marine Safety Unit Sturgeon Bay · USCG Great Lakes District (CGD-GL) · Activity 2829683
1 November 2006
Security Plan Amendment Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 2812385
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 6 August 2024
Resolved
In tank vessels carrying Grade A, B, C, or D liquid cargo, cargo pumps shall be isolated from source of vapor ignition by gas tight bulkheads. Marine Inspector observed cargo pump drive shaft seal leaking at bulkhead penetration on deck.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 28 August 2024
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 6 August 2024
Resolved
Periodic tests and inspection shall be made of the main and auxiliary machinery, boilers...the inspection and tests shall insure that the equipment and associated structure are in satisfactory operating conditions. Internal inspection of thermal fluid heater installed on board showed cracked/broken off refractory and missing insulation required for safe operation of the boiler. Make permanent repairs to boiler via boiler tech within 3 weeks and submit repair report to CG MI at completion.
Action required: 705 - Other - as specified
Resolved 28 August 2024
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 6 August 2024
Resolved
Except for vessels that are carrying only liquid cargoes containing less than 0.5% benzene by volume, this subpart applies to all Coast Guard inspected vessels that are carrying benzene containing liquids in bulk as cargo. This barge is certificated to carry benzene-containing liquids in bulk, therefore, vessel must comply with the regulations set forth in 46 CFR Part 197 Subpart C for benzene monitoring.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 28 August 2024
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 6 August 2024
Resolved
The general construction of the vessel shall be such as to minimize fire hazards insofar as is reasonable and practicable. CG MI observed missing lagging on Port Cargo Pump engine, port generator, and hydraulic system prime mover exhaust piping. Add lagging on aforementioned locations to the satisfaction of CG MI.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 28 August 2024
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 28 September 2020
Resolved
Each vessel vapor connection flange face must have a permanent stud projecting outward that has a .5 inch diameter and is at least 1 inch long. It must be located at the top of the flange face, midway between boltholes and in line with the bolthole pattern. There is no permanent stud on the vapor line flange. Permenently install stud in vapor line flange face.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 28 October 2020
Resolved 29 September 2020
Resolution: Permenent stud is installed on vapor control line.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 28 September 2020
Resolved
All tank vessels of 150 gross tons or over 79 feet in length or greater navigating the oceans or coastwise waters are subject to the regulations in parts 42 to 45, inclusive, subchapter E (load lines), of this chapter, as applicable. The ring, line,s and shall be permanently marked on the sides of the vessels. "S" for the summer load line is not permanently marked. Permanently mark/punch "S" for summer load line and be painted in contrasting color. 46CFR31.25-1
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 28 October 2020
Resolved 29 September 2020
Resolution: Documentation was recieved showing "S" was permanently marked and painted in contrasting color.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 28 September 2020
Resolved
All tank vessels are subject to the regulations contained in subchapter J of this subchapter. Electric installations on vessels must ensure: protection of passengers, crew, other persons, and the vessel from electrical hazards. There are naked and exposed wires in the machinery space/house. Remove wires or make/house wires in junction box. 46CFR31.35-1
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 28 October 2020
Resolved 29 September 2020
Resolution: Documentation was recieved showing all exposed dead end wiring was removed.
01 - Certificates & Documentation › 011 - Ships Certificates › Load Lines (including Exemption)
Issued 14 September 2018
Resolved
Load Line marking on Hull did not match Load Line Cert. 46CFR42.13-40
Action required: 10 - Deficiency Rectified
Due 14 September 2018
Resolved 14 September 2018
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 14 September 2018
Resolved
Electrical cables shall be listed as Marine Shipboard Cable. Cables to to pump engines are classified as Welding cables. Replace cables with marine shipboard cable. 46 CFR 111.60-1(a)
Action required: 10 - Deficiency Rectified
Due 14 September 2018
Resolved 14 September 2018
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 14 September 2018
Resolved
In general, connections and terminations to all conductors must retain the original electrical, mechanical flame-retarding, and where necessary, fire-resisting properties of the cable. 46 CFR 111.60-17.
Action required: 10 - Deficiency Rectified
Due 14 September 2018
Resolved 14 September 2018
Documentation › Logs/Records › Operational Procedures for Engines or Equipment
Issued 14 September 2017
Resolved
CREW UNABLE TO FOLLOW ONBOARD PSTP FOR SOME THERMAL FLUID HEATER TESTS. REVISE ONBOARD TEST PROCEDURES TO INCLUDE SPECIFIC DETAILS OF HOW TO PERFORM EACH REQUIRED TEST.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 22 December 2017
Resolved 17 November 2017
Resolution: Received new PSTPs, all satisfactory.
Electrical › Electrical Distribution System (service) › Circuit Breaker
Issued 7 June 2016
Resolved
Name plate for circuit breaker missing. 46 CFR 111.30-15
Action required: 705 - Other - as specified
Due 7 August 2016
Resolved 13 July 2016
Electrical › Electrical Distribution System (service) › Junction Box
Issued 7 June 2016
Resolved
Pyrometer wiring exposed due to conduit not properly installed in J-Box on Fluid Thermal Heater. 46 CFR 111.60
Action required: 705 - Other - as specified
Due 7 August 2016
Resolved 13 July 2016
Pollution Prevention/Response › Prevention Equipment › Cargo Monitor/Control System
Issued 7 June 2016
Resolved
Vessel has no loss of power to high level/overfill alarms. 46 CFR 39.20
Action required: 705 - Other - as specified
Due 7 July 2017
Resolved 6 December 2016
Resolution: Crew proved operation of loss of power alarm for high level/overfill alarms.
Documentation › Logs/Records › Operational Procedures for Engines or Equipment
Issued 7 June 2016
Resolved
Provide approved test procedures IAW manufacture instructions for fluid thermal heater.46 CFR 63.10-1
Action required: 705 - Other - as specified
Due 7 July 2017
Resolved 6 December 2016
Resolution: Crew proved oepration of all alarms/shutdowns for thermal fluid heater on board.
Deck/Cargo › Vapor Control Systems › Vapor Recovery Unit
Issued 15 January 2015
Resolved
Vapor Recovery Unit (VRU) shall not be placed in service until the required testing is witnessed and inspection is completed to the satisfaction of the attending Coast Guard Marine Inspector IAW 46 CFR 61.40-6.
Action required: 705 - Other - as specified
Due 15 July 2015
Resolved 4 March 2015
Deck/Cargo › Cargo Heating › General
Issued 3 November 2014
Resolved
Thermal Fluid Heater shall not be placed in service until the required testing is witnessed and inspection is completed to the satisfaction of the attending CG marine inspector IAW 46 CFR 61.30.
Condition: Invalid
Action required: 705 - Other - as specified
Resolved 15 January 2015
Resolution: Conducted satisfactory tests of Thermal Fluid Heater.
Construction/Loadline › Hull › Hull Plating
Issued 16 December 2013
Resolved
Prior to shifting, barge must have internal structural exam (ISE) and dive survey completed.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Due 19 December 2013
Resolved 17 December 2013
Resolution: ISE and dive survey completed and all sat w/ CG inspectors and ABS surveyor.
Stability › Incline Test › General
Issued 5 April 2012
Resolved
Provide proof of valid stability letter prior to carrying cargo. 46 CFR 170.120
Due 30 November 2012
Resolved 2 November 2012
Resolution: Received valid stability letter from ABS.
Deck/Cargo › Vapor Control Systems › Vapor Recovery Unit
Issued 2 December 2011
Resolved
Prior to operating the vapor recovery system, conduct an operational test in the presence of a CG Marine Inspector. 46 CFR 31.10-15
Action required: 705 - Other - as specified
Due 2 January 2012
Resolved 9 December 2011
Resolution: Witnessed operational chech of vapor recovery system. All satisfactory. R. [name withheld], CWO
Pollution Prevention/Response › Prevention Equipment › Cargo Monitor/Control System
Issued 2 December 2011
Resolved
Disconnect radar cargo gauging system and submit drawings and certificates to the MSC for verification of approvals or install USCG approved system. 46 CFR 39. 20-3 and 46 CFR 111.105.-7
Action required: 705 - Other - as specified
Due 2 March 2012
Resolved 25 October 2012
Deck/Cargo › Holds/Tanks › Tank Level Monitoring Device
Issued 2 December 2011
Resolved
Portable electric equipment must not be used in hazardous locations unless it is approved by testing laboratories recognized by the USCG. (Hermetic utimeter portable gauging gun is not approved. Provide the FM approval number and or testing results and procedures to the MSC.) 46 CFR 35. 30-30
Action required: 705 - Other - as specified
Due 2 March 2012
Resolved 27 December 2011
Resolution: Received the FM approvals for the Hermetic portable gauging equipment. The Hermetic portable gauging device is approved by IECEx discussed with the MSC.
Electrical › Lighting (service) › Lighting Fixture
Issued 8 April 2010
Resolved
Relocate light in vestibule between the diesel room & VPU room IWO piping interference.
Due 8 May 2010
Resolved 28 May 2010
Deck/Cargo › Vapor Control Systems › Vessel Vapor Overpressure/Vacuum Protection
Issued 8 April 2010
Resolved
Prove proper operation of remote alarm lights & horn/siren.
Due 8 May 2010
Resolved 8 May 2010
Engineering › Compressed Air System (control) › Piping
Issued 8 April 2010
Resolved
Submit for local approval plans to hardwire electric supply to air compressor dryer.
Due 8 May 2010
Resolved 8 May 2010
Engineering › Compressed Air System (control) › Piping
Issued 8 April 2010
Resolved
Install and prove proper operation of dryer after approval of item #3. (the plan approval)
Due 8 May 2010
Resolved 8 May 2010
Operations/Management › Cargo Transfer/Lightering › Use of Vapor Control System
Issued 8 April 2010
Resolved
Provide proof of Periodic Safety Test Procedure for the Vapor Processing Unit.
Action required: 705 - Other - as specified
Resolved 20 July 2010
Resolution: Received PTP for VPU
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 2 April 2010
Resolved
Complete plan approval and testing on the Vapor Processing Unit. Plan approval and testing includes comments and direction included in the following letters from the USCG Marine Safety Center (MSC) to Harley Marine Services:
MSC E1-0902725 dated 30 Sep 2009, MSC E2-0902795 dated 09 Oct 2009, MSC E1-0902844 dated 15 Oct 2009, and
MSC Letter E2-0902920 dated 28 Oct 2009. (Con't in item #2)....
Due 2 June 2010
Resolved 8 April 2010
Resolution: Items 1 & 2 are one requirement. Cleared with sat test of Design Verification Test Procedures witnessed in conjuction with inspector from Sector LA/LB.
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 2 April 2010
Resolved
(this is continued from item #1): The Vapor Processing Unit must remain segregated from all other vessel cargo systems and may not be operated until all parts of the Vapor Processing System have been approved and the systems, installation and testing are to the satisfaction of an attending marine inspector from [name withheld] - Long Beach.
Due 2 June 2010
Resolved 8 April 2010
Resolution: Items 1 & 2 are one requirement. Cleared with sat test of Design Verification Test Procedures witnessed in conjuction with inspector from Sector LA/LB.
Deck/Cargo › Vapor Control Systems › Vapor Recovery Unit
Issued 24 July 2009
Resolved
Submit plans for the Vapor Processing Unit and all associated systems and components, to the Marine Safety Center for approval. The Vapor Processing Unit must remain segregated from all other vessel cargo systems and may not be operated until all plans are approved and the system ins installed to the satisfaction of an attending marine inspector.
Action required: 705 - Other - as specified
Due 11 January 2010
Resolved 25 February 2010
Deck/Cargo › Vapor Control Systems › Vapor Destruction Unit
Issued 19 March 2009
Resolved
Make permanent repairs to Vapor Processing Unit (VPU) prior to its use, and ensure system is segregated from the vapor recovery system. Provide report describing the cause of the fire in the VPU.
Action required: 705 - Other - as specified
Due 19 April 2009
Resolved 24 July 2009
Resolution: Issued new requirement for submission of system plans to the MSC for approval.
Engineering › Pressure Vessel › Marking and Stamping
Issued 19 March 2009
Resolved
Provide plans and manufacturers data reports for all class I, II and III pressure vessels installed or configured for use on the barge, including the vapor processing system, for review by a marine inspector, in accordance with 46 CFR 54.10. This item must be corrected before any applicable pressure vessel is subjected to more than 15 psi internal pressure.
Action required: 705 - Other - as specified
Due 30 April 2009
Resolved 24 July 2009
Resolution: Issued new requirement for submission of system plans to the MSC for approval.
Deck/Cargo › Vapor Control Systems › Vapor Recovery Unit
Issued 12 June 2008
Resolved
Demonstrate full operations and safety shutdown devices prior to utilization of system.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 7 January 2009
Resolved 25 September 2008
Resolution: All installed safety devices were tested sat per Certifying Entity letter of 22Sep08.
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 12 June 2008
Resolved
Provide piping weld procedures for review and coupon for testing and approval to OCMI, prior to placing Vapor Control System in service.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 7 August 2008
Resolved 22 July 2008
Documentation › Safety/Response Plans/Programs › SOPEP
Issued 11 December 2006
Resolved
Prior to carrying cargo, provide an approved copy of the Shipboard Oil Pollution Emergency Response plan (SOPEP) and Vessel Response Plan.
Condition: Unknown
Action required: 701 - Prior to carriage of passengers/cargo
Due 10 January 2007
Resolved 20 December 2006
Resolution: Received phone call from vessel rep [name withheld], and confirmed with MSC-VRP division, plans were approved. Cleared CG-835.
Engineering › Diesel Engine (auxiliary) › Turbocharger
Issued 6 December 2006
Resolved
IAW 46CFR58.10-10(a) & 46CFR58.10-5(a) change engine components or replace the three Model 4045H John Deere engines (2 generators & 1 hydraulic pump engine) to "marine type" engines.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Resolved 9 February 2007
Resolution: See email in Documents (PCV Email Marine Engine.doc) from G-PCV-1 to MSD Sturgeon Bay referencing ABS determination of engine to be suitable for application iaw 46 CFR 58.10-5(a).