Records from 2015 to 2025. Most recent: inspection, 23 October 2025.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 13.0 ft
Registered tonnagegross 1,754 / net 1,754
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderJEFFBOAT LLC · JEFFERSONVILLE, IN, UNITED STATES · built 2015
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portHOUSTON, TX
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 8 October 2025 · expires 30 November 2026
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1754 - Simplified, Gross Ton
1754 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 15
23 October 2025
MTSA Verification · Cargo Tank Internal · Examination of Repairs · Internal Structural Exam · Drydock Exam · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8257578
29 December 2023
Examination of Repairs · MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7841724
1 September 2021
Deficiency Check · Administrative Inspection · Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7302310
30 August 2021
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7335095
28 September 2020
MTSA Verification · Internal Structural Exam · Examination of Repairs · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7066864
12 March 2020
Type not recorded
No type recorded · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 6926219
16 January 2020
MTSA Verification · Annual Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6891037
28 November 2019
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6867131
7 December 2018
MTSA Verification · Periodic Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6592890
22 November 2017
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6327388
20 July 2017
Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6216267
10 February 2017
Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6085919
23 January 2017
Deficiency Check
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6077462
20 January 2017
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6076929
6 July 2015
Administrative Inspection · Cargo Tank Internal · Initial Construction-Excluding Oversight · Examination of Repairs · Internal Structural Exam · MTSA Verification · Hull Examination · Initial Certification · Deadweight Survey
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 5191091
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 1 September 2021
Resolved
All tank vessels shall conform to the requirements in this subpart in construction of hulls.
Vsl was reported to be aground due to hurricane IDA.
Vsl shall provide salvage plan to the satisfaction of the CG prior to conducting salvage operations.
After salvage is complete and vsl is re-floated, a one time transit is authorized to repair facility. 46 CFR 32.60-1(a)
Condition: Damaged By Earlier Event
Action required: 60 - Rectify deficiencies prior to movement
Due 30 October 2021
Resolved 12 October 2021
Resolution: Conducted satisfactory inspection IAW attached repair plan. All sat.
Communications › Visual Communication › Signalling Lamp
Issued 20 January 2017
Resolved
Prove proper operation of Red warning light on the Thermal Fluid heater.
Condition: Improper/Lack of Maintenance
Due 20 January 2017
Resolved 20 January 2017
Resolution: Tech rep replaced light prior to completion of inspection
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Communications
Issued 20 January 2017
Resolved
Prove proper operation of High Level overfill device.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 January 2017
Resolved 23 January 2017
Construction/Loadline › Hull › Hull Plating
Issued 20 January 2017
Resolved
Gas free bow void space and make ready for inspection for damage of internals and hull plating. (Damage may extend into the No. 1 void)
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Due 25 February 2017
Resolved 15 February 2017
Resolution: M/I attended barge at shipyard and completed examination and oversight of repairs. Found satisfactory to the attending M/I, cleared 835. See AN 6085919 for details.
Electrical › Electrical Distribution System (service) › Ground Detection
Issued 20 January 2017
Resolved
Revise electrical one line drawing to address the instalation of a ground conductor between the barges, that an electrical interlock is provided between the 100 amp overboard power circuit breaker and the 100 amp TFH circuit breaker and that suitable ground detection is installed on the distribution system. 46 CFR 110.25-1, 46 CFR 111.05-3(D) 46 CFR 111.05-25 AND 46 CFR 111.107
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 August 2017
Resolved 20 July 2017
Resolution: Verified installation of safety ground, ground detection system, and installation of a 150 amp breaker according to plans approved by MSC so that the installation of electrical interlock was not required.