Inspection history · 60
8 October 2024
Drydock Exam · COI Inspection · Examination of Repairs · Internal Structural Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8016187
24 May 2023
Administrative Inspection
Administrative · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7695838
20 January 2023
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7624515
6 August 2022
Damage Survey · Examination of Repairs · Deficiency Check · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7525901
13 July 2022
Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7505635
29 September 2021
Damage Survey · Administrative Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 7323218
1 September 2021
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7302298
30 August 2021
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7335095
26 July 2021
MTSA Verification · Periodic Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7258216
12 September 2019
COI Inspection · Cargo Tank Internal · MTSA Verification · Internal Structural Exam · Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6805404
9 June 2019
Damage Survey · Administrative Inspection
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 6709225
6 June 2019
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 6712910
30 April 2019
Examination of Repairs · Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6670558
17 April 2019
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6664739
16 November 2018
Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 6581956
13 November 2017
Annual Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6305648
9 November 2016
MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6037025
2 October 2016
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 6017056
24 May 2016
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 5901260
5 November 2015
Deficiency Check · MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 5760187
15 July 2014
Examination of Repairs · Internal Structural Exam · COI Inspection · Hull Examination · MTSA Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4916771
25 May 2014
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4945828
11 September 2013
Deficiency Check
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 4712194
24 August 2013
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 4697948
15 August 2013
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 4698038
12 August 2013
Damage Survey · MTSA Verification · Annual Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4682963
10 August 2012
Deficiency Check · Annual Inspection
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 4404282
27 March 2012
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4273274
1 March 2012
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4254637
12 February 2012
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 4243798
8 November 2011
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4184922
3 October 2011
Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4157277
3 October 2011
MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4160305
25 July 2011
Type not recorded
No type recorded · Marine Safety Detachment Quad Cities · USCG Heartland District (CGD-H) · Activity 4094719
25 July 2011
Damage Survey
Physical examination · Marine Safety Detachment Quad Cities · USCG Heartland District (CGD-H) · Activity 4094868
21 July 2011
Type not recorded
No type recorded · Marine Safety Detachment St. Paul · USCG Heartland District (CGD-H) · Activity 4090362
1 June 2010
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3755932
16 June 2009
MTSA Verification · Internal Structural Exam · Drydock Exam · Examination of Repairs · Cargo Tank Internal · COI Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3500287
4 December 2008
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3374959
17 November 2008
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3364524
16 October 2008
Administrative Inspection
Administrative · Commandant (CG-CVC) · Activity 3345681
14 July 2008
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3267762
24 April 2008
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3192013
5 January 2008
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3125246
16 November 2007
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3115816
17 July 2007
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2998250
15 June 2007
Deficiency Check
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 2962701
4 March 2007
Deficiency Check
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 2881916
26 February 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2877635
25 February 2007
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2897594
22 February 2007
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2875673
29 August 2006
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 2763194
5 January 2006
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 2569363
10 November 2005
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 2532277
8 November 2005
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 2532246
11 July 2005
Annual Inspection · MTSA Verification
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2419513
8 July 2005
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 2419380
2 November 2004
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 2233235
26 June 2004
Initial Construction-Excluding Oversight · Initial Certification · Hull Examination · Internal Structural Exam · Cargo Tank Internal
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 2114881
2 June 2004
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 2086452
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 1 September 2021
Resolved
All tank vessels shall conform to the requirements in this subpart in construction of hulls.
Vsl received hull damage during hurricane IDA
Vessel is authorized one time transit to repair facility.
46CFR32.60-1(a)
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 15 October 2021
Resolved 29 September 2021
Resolution: Vsl commenced repairs at Bollinger Amelia Shipyard
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 26 July 2021
Resolved
Any tank vessel which is equipped with an internal combustion engine driven cargo pump on the weather deck shall be provided with a minimum of one remote manual shutdown station, conspicuously marked, and located at the midpoint of such vessel, or 100 feet from the engine, whichever is the more practical. Prove proper operation of remote shutdown.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 28 July 2021
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 17 April 2019
Resolved
THE REGULATIONS IN THIS SUBCHAPTER CONTAIN REQUIREMENTS
FOR CONSTRUCTION. BARGE HAS SMALL PUNCTURE/WELD FRACTURE BELOW THE WATERLINE IVO PORT STERN BOTTOM CORNER WRAP. VESSEL IS PERMITTED TO TRANSIT TO CITGO IN LAKE CHARLES, LA AND DISCHARGE ITS CURRENT CARGO. VESSEL IS NOT PERMITTED TO CONDUCT FURTHER CARGO OPS UNTIL PERMANENT REPAIRS TO THE DAMAGED STERNBOX ARE MADE TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2019
Resolution: Verified appropriate repairs had been made and witnessed a satisfactory air test of applicable areas. Test results were to satisfaction of attending Marine Inspector.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 16 November 2018
Resolved
Emergency shutdown for starboard cargo pump engine inoperative.
Action required: 10 - Deficiency Rectified
Due 16 November 2018
Resolved 16 November 2018
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 16 November 2018
Resolved
Fuel supply and return valves for both cargo pump engines, thermal fluid heater, and generator have no indicators for open or closed.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 30 November 2018
Resolved 16 November 2018
Resolution: new valves were put in place
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Gauges, thermometers, etc
Issued 16 November 2018
Resolved
Port side cargo header gauge has broken needle and is unreadable from the control station. Replace prior to cargo operations.
Action required: 705 - Other - as specified
Due 16 November 2018
Resolved 16 November 2018
Resolution: gauge was replaced
Stability › Weathertight Integrity › General
Issued 5 November 2015
Resolved
Repair/Replace void hatch cover closure device on stern void to original specification to satisfaction of OCMI. 46 CFR 31.10-17(a)(3) & 33 CFR 155.815
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 5 December 2015
Resolved 6 November 2015
Resolution: Void was verified gas free by marine chemist, hatch closure holder for dog was welded to hatch as originally designed. Hatch cover seals properly with all 4 dogs as designed.
Construction/Loadline › Hull › Hull Plating
Issued 12 August 2013
Resolved
called out 4 inch sharp set-in cylindrical in nature between headlog and starboard pushknee on bowrake. Believe damage caused by another barge's locking pin.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 26 September 2013
Resolved 14 September 2013
Resolution: Water pressure test conducted on repair. All Sat.
Engineering › Fuel Oil Service System › Hose
Issued 10 August 2012
Resolved
Repair Small fuel leak on Generator.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Due 12 September 2012
Resolved 10 August 2012
Resolution: Tightened fittings. Tested SAT
Engineering › Compressed Air System (start air) › Receiver/Bottle
Issued 10 August 2012
Resolved
Provide vessel start air receiver information from manufacturer.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 10 September 2012
Resolved 5 September 2012
Resolution: Provided information for review. All SAT.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Relief Valve
Issued 10 August 2012
Resolved
Provide documentation of safety relief valve test.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 10 September 2012
Resolved 5 September 2012
Resolution: Provided copy of test.
Engineering › Diesel Engine (auxiliary) › Emergency shutdown
Issued 10 August 2012
Resolved
Prove proper operation of emergency shutdown.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 10 August 2012
Resolution: Conducted repair on the spot and tested SAT.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 10 August 2012
Resolved
Install position indicators for cargo pipe valves.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 10 August 2012
Resolved 10 August 2012
Resolution: Installed new indicator on valve.
Electrical › Electrical Distribution System (service) › Wiring
Issued 3 October 2011
Resolved
Make repairs to the intrinsically safe electrical distribution system located in the hazardous areas by 05 OCT 2011.
Action required: 705 - Other - as specified
Due 5 October 2011
Resolved 4 October 2011
Resolution: Receieved technician''s report, cleared deficiency.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 3 October 2011
Resolved
Vessel failed to conduct a periodic inspection of a tank vessel IAW 46 CFR 31.10-17(a).
Action required: 705 - Other - as specified
Due 3 October 2011
Resolved 3 October 2011
Resolution: Conducted a periodic inspection and endorsed COI. Cleared deficiency.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 3 October 2011
Resolved
Vessel requires an annual inspection and is 3 months past the anniversary date.
Action required: 705 - Other - as specified
Due 3 October 2011
Resolved 3 October 2011
Resolution: Annual inspection completed by Sector Houston-Galveston (MSU Texas City)
Construction/Loadline › Structures › Scuttle
Issued 25 July 2011
Resolved
Replace damaged Void cover on the NO.9 Starboard Void.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 25 August 2011
Resolved 10 August 2012
Resolution: Vessel has conducted a periodic exam and a annual exam by 2 different offices, the most recent narrative stated that 0 defs remain outstanding from previous exams.
Documentation › Safety/Response Plans/Programs › Vessel Response Plan
Issued 13 August 2008
Resolved
Vessel resubmission is overdue. The TVRP must be amended to verify intended areas of operation/COTP zones, identify contact information for border states, and per reg 33 CFR 155.1035(j) include individual capacities of fuel, lube, and ballast tanks or state "not applicable" before approval is granted.
Due 13 September 2008
Resolved 3 February 2009
Resolution: Vessel resubmission approved 2/3/2009 with revisions received 1/28/2009. New vessel VRP expiration date 2/28/2014.
Construction/Loadline › Structures › Rake
Issued 26 February 2007
Resolved
4" inset, 2 feet long, located in the port side gunwale area in the vicinity of the #3 wing tank
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 12 March 2007
Resolved 12 March 2007
Resolution: 3/1/07 c/r 5" x 20" x 3/8 gunnel . Work completed by blood worth Marine Corpus Christy TX.